Short-Form System Reference Guide: Wastewater Treatment Plants
Use this guide to choose a coating system by substrate, exposure and service condition. It is a selection reference, not a bid-ready specification. The full guide is below, and a PDF copy is free to download.
Download the PDF: the file is attached at the end of this page.
For bid documents: use the companion Section 09 96 23 High-Performance Coatings, Wastewater Treatment guide specification, or ask ACC for a specification tailored to your project.
Questions: atlantic@tnemec.com or 484-644-5303.
Reader's Note
Use this guide to quickly select a coating or lining system by plant area, substrate, and exposure. It is a selection reference for operations, facilities/asset management, and project teams; it is not a bid-ready specification.
For bid or construction documents, use the companion CSI 3-part specification, Section 09 96 23 - High-Performance Coatings and Linings (Wastewater Treatment), or contact ACC for project-specific guidance.
Prepared as a service by: Atlantic Coating Consultants | Wally Bates | atlantic@tnemec.com | 484-644-5303
Overview
1. Purpose
This guide summarizes wastewater treatment coating and lining for new and existing steel and ductile iron in immersion, splash, fume and atmospheric service; digester lids and interiors; concrete immersion, splash and headspace linings; secondary containment; condensation mitigation; and the shared interior, exterior and resinous flooring systems used in plant buildings and support spaces.
2. How to Use This Guide
Start with the Quick Locator Index if you know the plant area or component. Find the applicable system in the schedule below.
If you know the substrate and exposure, go directly to the system tables and match the Condition and Typical Locations.
Use Surface Preparation, Coat Schedule, and Total Build for budgeting and work-order planning.
Contact ACC to confirm project-specific exposure, chemical service, surface condition, color coding, or full CSI specification requirements.
3. Basis of Design
Products scheduled herein are manufactured by Tnemec Company, Inc. and Epoxytec (part of the Tnemec family of coatings and linings), and are listed as the basis of design for the performance, appearance, and warranty characteristics described.
4. Not Covered in This Guide
Architectural coatings for non-process administration/office spaces are summarized here only as shared systems; see the companion Architectural guide for the full set. Secondary containment coverage is limited to the chemicals listed in WW-C2.1; contact ACC for other chemical exposures.
5. General Application & Warranty Notes
Follow the current Tnemec product data sheet for substrate, ambient, dew-point, humidity, ventilation, and application requirements.
Verify dry film thickness during and after application. For immersion, lining, and resinous flooring work, consider a mock-up or field sample before full-scale application.
Comply with applicable confined-space entry, ventilation, and atmospheric-monitoring requirements for enclosed process structures.
Tnemec warranty terms vary by system and project; contact ACC or Tnemec to confirm applicable coverage.
Quick Locator Index
Find a system by where it goes. Confirm project-specific conditions before final selection.
Plant Area / Component | Applicable System |
ADMINISTRATION / CONTROL / OFFICE BUILDING | |
Interior support spaces — the exterior envelope is covered in the companion Architectural guide (Section 09 96 00), not here. | |
Interior Walls (Gypsum Wallboard) | Gypsum board wall systems are not covered in this guide — see the companion Architectural guide (Section 09 96 00). |
Resinous Flooring | • 100% Solids Epoxy — 1/16" Solid Color Epoxy Broadcast — Light Duty • Water-Based Epoxy — 1/16" Solid Color Epoxy Broadcast — Light Duty • 100% Solids Epoxy — 1/8" Solid Color Epoxy Broadcast — Moderate Duty • Water-Based Epoxy — 1/8" Solid Color Epoxy Broadcast — Moderate Duty |
HEADWORKS / SCREENING / GRIT REMOVAL / INFLUENT STRUCTURES | |
Enclosed, elevated H₂S/MIC exposure. | |
Concrete Walls & Structure | • Elevated H2S / MIC, High-Build Epoxy Lining • Moderate to Severe Deterioration / I&I, Structural Epoxy Lining (Epoxytec) |
Steel Tanks, Pipes & Equipment | • New — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments • Existing — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments • New — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) • Existing — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) |
PVC & Insulated Pipe | • PVC Pipe, Trim and Plastic Components • Insulated Pipe Jacketing (Canvas / PVC Jacket) |
Resinous Flooring (Below-Grade / MVT Areas) | • Urethane Cement — 1/8" Solid Color Urethane Cement — Moderate/Heavy Duty |
WET WELLS / PUMP STATIONS | |
Concrete (Wet Well, Enclosed) | • Elevated H2S / MIC, High-Build Epoxy Lining • Moderate to Severe Deterioration / I&I, Structural Epoxy Lining (Epoxytec) |
Steel Tanks, Pipes & Equipment | • New — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments • Existing — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments • New — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) • Existing — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) |
Ductile Iron Pipe, Valves & Fittings | • New — Ductile Iron Pipe, Valves and Fittings — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) • Existing — Ductile Iron Pipe, Valves and Fittings — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) |
Resinous Flooring (Pump Station Dry Pit) | • Urethane Cement — 1/4" Solid Color Urethane Cement — Heavy Duty |
AERATION BASINS / OXIDATION DITCHES / SECONDARY CLARIFIERS | |
Open or well-ventilated, low-to-moderate H₂S exposure. | |
Concrete Structure | • Light to Moderate Wastewater Exposure, Epoxy Lining |
Steel Equipment & Structural (Non-Immersion) | • New — Structural Steel, Tanks and Equipment — Exterior, Non-Immersion • Existing — Structural Steel, Tanks and Equipment — Exterior, Non-Immersion • New Steel — Moderate Duty, Solvent Based Epoxy • Previously Painted Steel — Moderate Duty, Solvent Based Epoxy Finish |
Resinous Flooring (Blower / Mechanical Building) | • Urethane Cement — 1/4" Solid Color Urethane Cement — Heavy Duty |
DIGESTERS / SLUDGE HOLDING & STORAGE / COVERED PRIMARY TREATMENT | |
Enclosed, elevated H₂S/MIC exposure. | |
Concrete Structure | • Mesophilic Digester, Concrete — Exposed Concrete Walls and Floors, Medium Build • Mesophilic Digester, Concrete — Underside of Digester Lid and Rim Skirt, High Build • Thermophilic Digester, Concrete — Exposed Concrete Walls and Floors, Medium Build • Elevated H2S / MIC, High-Build Epoxy Lining |
Steel Tanks & Piping | • Mesophilic Digester, Steel — Underside of Digester Lid and Rim Skirt, Medium Build • Mesophilic Digester, Steel — Underside of Digester Lid and Rim Skirt, High Build • Mesophilic Digester, Steel — Top of Lid, Exterior Exposed • Thermophilic Digester, Steel — Underside of Digester Lid and Rim Skirt, Medium Build • New — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments • Existing — Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments |
Resinous Flooring (Below-Grade / MVT Areas) | • Urethane Cement — 1/8" Solid Color Urethane Cement — Moderate/Heavy Duty |
CHEMICAL FEED & STORAGE BUILDINGS / SECONDARY CONTAINMENT | |
Secondary Containment Lining | • Reinforced Novolac / Vinyl Ester Lining — Acid, Caustic, Oxidizer, Coagulant, Dechlorination, Organic |
CMU / Concrete Walls | • New CMU — Moderate/Heavy Duty, Chemical Resistant • New Concrete — Moderate/Heavy Duty, Chemical Resistant • Previously Painted CMU/Concrete — Moderate/Heavy Duty, Chemical Resistant • New CMU — Moderate Duty, Water Based • Previously Painted CMU/Concrete — Moderate Duty, Water Based • Exterior CMU/Concrete, Uncoated — Elastomeric / Crack-Bridging, Smooth Finish • Exterior CMU/Concrete, Previously Painted — Elastomeric / Crack-Bridging Recoat |
Chemical Piping & Tanks (Steel) | • New Steel — Heavy Duty, Chemical Resistant Epoxy • Previously Painted Steel — Heavy Duty, Chemical Resistant Epoxy |
Resinous Flooring (Building Floor, Outside Containment) | • Urethane Cement — 1/4" Solid Color Urethane Cement — Heavy Duty |
PIPING GALLERIES / YARD & PROCESS PIPING | |
Steel Pipe, Shop- or Field-Coated | • New — Steel Pipe — Exterior OD, Non-Immersion (Shop or Field Coated) • Existing — Steel Pipe — Exterior OD, Non-Immersion (Shop or Field Coated) • New — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) • Existing — Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) • New — Ductile Iron Pipe, Valves and Fittings — Exterior OD, Non-Immersion (Shop or Field Coated) • Existing — Ductile Iron Pipe, Valves and Fittings — Exterior OD, Non-Immersion (Shop or Field Coated) |
Galvanized Pipe & Fabrications | • Galvanized Steel — New or Full Coating Removal, Urethane Finish (Good) • Galvanized Steel — Previously Coated Galvanized, Overcoat • New Steel — Galvanized Steel, Epoxy Finish • New Steel — Galvanized Steel, Urethane Finish • Previously Painted Steel — Galvanized Steel, Epoxy Finish • Previously Painted Steel — Galvanized Steel, Urethane Finish |
Insulated Pipe (Jacketing) | • Insulated Pipe Jacketing (Canvas / PVC Jacket) |
PVC Pipe | • PVC Pipe, Trim and Plastic Components |
Resinous Flooring (Gallery / Tunnel Floor) | • Urethane Cement — 1/8" Solid Color Urethane Cement — Moderate/Heavy Duty |
EXTERIOR TANKS, EQUIPMENT & STRUCTURAL STEEL (SITE-WIDE) | |
Structural Steel, Tanks, Pipes & Equipment | • New — Structural Steel, Tanks and Equipment — Exterior, Non-Immersion • Existing — Structural Steel, Tanks and Equipment — Exterior, Non-Immersion • Exterior New Steel — Zinc / Epoxy / Urethane (Good) • Exterior Steel Overcoat — Epoxy Mastic / Urethane (Good) |
Condensation-Prone Metal (Chilled Lines, Enclosures) | • Aerogel Insulative Coating on Steel Pipe, Tanks and Structure |
Resinous Deck Coating (Elevated Walkways & Platforms) | The elevated/exterior pedestrian deck coating (System WP1.1) is in the companion Resinous Flooring guide (Section 09 67 23). |
INTERIOR / EXTERIOR SUPPORT BUILDINGS (UTILITY & MECHANICAL ROOMS) | |
Interior CMU / Concrete Walls | • New CMU — Moderate Duty, Water Based • New CMU — Moderate Duty, Solvent Based • New CMU — Moderate/Heavy Duty, Water Based w/ Urethane Finish • New CMU — Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish • New Concrete — Moderate Duty, Water Based • New Concrete — Moderate/Heavy Duty, Water Based w/ Urethane Finish • Previously Painted CMU/Concrete — Moderate Duty, Water Based • Previously Painted CMU/Concrete — Moderate/Heavy Duty, Water Based w/ Urethane Finish • Previously Painted CMU/Concrete — Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish • Concrete Ceilings — Dry-Fall, High-Moisture / Natatorium Ceilings |
Exterior CMU / Masonry Walls | • Exterior CMU/Concrete, Uncoated — Elastomeric / Crack-Bridging, Smooth Finish • Exterior CMU/Concrete, Previously Painted — Elastomeric / Crack-Bridging Recoat • Sealer — Penetrating Silane/Siloxane Water Repellent |
Resinous Flooring (Mechanical Room Floor) | • Urethane Cement — 1/4" Solid Color Urethane Cement — Heavy Duty • 100% Solids Epoxy — 1/8" Solid Color Epoxy Broadcast — Moderate Duty |
Wastewater Treatment Plant Coating Systems
Includes wastewater-specific systems (WW-NS1 through WW-S3) and the shared interior, exterior and resinous flooring systems from Sections 09 96 00 and 09 67 23. System codes are ACC's standard system codes and match Section 09 96 23.
Condition | Typical Locations | Surface Preparation | Coat Schedule (Product — DFT) | Total Build |
WASTEWATER-SPECIFIC SYSTEMS | ||||
WW-NS1 — NEW STEEL AND DUCTILE IRON | ||||
Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments WW-NS1.1 | New steel tanks, clarifier mechanisms, gates, weirs, baffles, launders, piping and equipment in wastewater immersion, splash and headspace service | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch Up: Series 1 Omnithane — 2.5–3.5 mils DFT Stripe Coat: Series V69 Hi-Build Epoxoline II — 3.0–5.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 142 Epoxoline — 14.0–16.0 mils DFT | 20.5–25.5 mils DFT (excludes stripe/touch-up coats) |
Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) WW-NS1.2 | Immersion service, non-potable (non-NSF) applications | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 12.0–18.0 mils DFT |
Ductile Iron Pipe, Valves and Fittings — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) WW-NS1.3 | Immersion service, non-potable (non-NSF) applications | Reference NAPF 500-03-04 | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 12.0–18.0 mils DFT |
Structural Steel, Tanks and Equipment — Exterior, Non-Immersion WW-NS1.4 | New exterior structural steel, tank exteriors, pipe supports, handrails, platforms and equipment in non-immersion atmospheric service | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch Up: Series 1 Omnithane — 2.5–3.5 mils DFT Stripe Coat: Series V69 Hi-Build Epoxoline II — 3.0–5.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 8.5–12.5 mils DFT (excludes stripe/touch-up coats) |
Steel Pipe — Exterior OD, Non-Immersion (Shop or Field Coated) WW-NS1.5 | Shop-primed steel pipe, field recoat — exterior, non-immersion service (yard piping, exposed transmission/distribution piping) | SSPC-SP6/NACE No. 3 (shop); lightly scarify shop coat, clean and dry (field) | Primer: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 9.0–13.0 mils DFT |
Ductile Iron Pipe, Valves and Fittings — Exterior OD, Non-Immersion (Shop or Field Coated) WW-NS1.6 | New ductile iron pipe, valves and fittings — exterior, non-immersion service (yard piping, exposed piping in galleries and pump rooms) | Reference NAPF 500-03-04 | Primer: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 9.0–13.0 mils DFT |
WW-ES1 — EXISTING STEEL AND DUCTILE IRON | ||||
Structural Steel, Tanks and Equipment — Wastewater Immersion, Splash, Fume Environments WW-ES1.1 | Existing steel tanks, clarifier mechanisms, gates, weirs, piping and equipment being recoated for wastewater immersion, splash and headspace service | Remove existing coating; SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Stripe Coat: Series V69 Hi-Build Epoxoline II — 3.0–5.0 mils DFT Finish Coat: Series 142 Epoxoline — 14.0–16.0 mils DFT | 18.0–22.0 mils DFT (excludes stripe coats) |
Steel Pipe — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) WW-ES1.2 | Immersion service, non-potable (non-NSF) applications | Remove existing coating; SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 12.0–18.0 mils DFT |
Ductile Iron Pipe, Valves and Fittings — Wastewater Immersion, Splash, Fume Environments (Shop or Field Coated) WW-ES1.3 | Immersion service, non-potable (non-NSF) applications | Remove existing coating; reference NAPF 500-03-04 | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 12.0–18.0 mils DFT |
Structural Steel, Tanks and Equipment — Exterior, Non-Immersion WW-ES1.4 | Existing exterior structural steel, tank exteriors, pipe supports, handrails, platforms and equipment being recoated for non-immersion atmospheric service | SSPC-SP2/SP3 Hand/Power Tool Cleaning; SSPC-SP11 to bare metal at corroded areas | Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Stripe Coat: Series V69 Hi-Build Epoxoline II — 3.0–5.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 10.0–15.0 mils DFT (excludes stripe coats) |
Steel Pipe — Exterior OD, Non-Immersion (Shop or Field Coated) WW-ES1.5 | Shop-primed steel pipe, field recoat — exterior, non-immersion service (yard piping, exposed transmission/distribution piping) | SSPC-SP2/SP3 Hand/Power Tool Cleaning; SSPC-SP11 to bare metal at corroded areas | Primer: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 9.0–13.0 mils DFT |
Ductile Iron Pipe, Valves and Fittings — Exterior OD, Non-Immersion (Shop or Field Coated) WW-ES1.6 | Existing ductile iron pipe, valves and fittings being recoated — exterior, non-immersion service (yard piping, exposed piping in galleries and pump rooms) | SSPC-SP2/SP3 Hand/Power Tool Cleaning; SSPC-SP11 to bare metal at corroded areas | Primer: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT | 9.0–13.0 mils DFT |
WW-MDS1 — STEEL MESOPHILIC DIGESTER - LIDS AND COMPONENTS | ||||
Underside of Digester Lid and Rim Skirt, Medium Build WW-MDS1.1 | Underside of steel mesophilic digester covers, lids and rim skirts — headspace exposure, medium-build lining | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Stripe Coat: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Finish Coat: Series 61 Tneme-Liner — 8.0–12.0 mils DFT | 12.0–18.0 mils DFT (excludes stripe coats) |
Underside of Digester Lid and Rim Skirt, High Build WW-MDS1.2 | Underside of steel mesophilic digester covers, lids and rim skirts — headspace exposure, high-build lining | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Stripe Coat: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Finish Coat: Series G435 Perma-Glaze — 15.0–20.0 mils DFT | 19.0–26.0 mils DFT (excludes stripe coats) |
Top of Lid, Exterior Exposed WW-MDS1.3 | Exterior (top) surfaces of steel digester lids and covers exposed to weather | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Stripe Coat: Series V69 Hi-Build Epoxoline II — 3.0–5.0 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 2.0–3.0 mils DFT Note: silica sand or glass beads can be added into this system for added slip resistance. Contact Atlantic Coating Consultants for more information. | 8.5–12.5 mils DFT (excludes stripe coats) |
WW-TDS1 — STEEL THERMOPHILIC DIGESTERS - LIDS AND COMPONENTS | ||||
Underside of Digester Lid and Rim Skirt, Medium Build WW-TDS1.1 | Underside of steel thermophilic digester covers, lids and rim skirts — elevated-temperature headspace exposure | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning, min. 3.0-mil angular profile | Primer: Series 1407 Vinester — 2.0–6.0 mils DFT Intermediate Coat: Series 1436 Vinester — 20.0–25.0 mils DFT Finish Coat: Series 1436 Vinester — 20.0–25.0 mils DFT | 42.0–56.0 mils DFT |
WW-C1 — CONCRETE — IMMERSION, SPLASH AND HEADSPACE | ||||
Light to Moderate Wastewater Exposure, Epoxy Lining WW-C1.1 | Concrete wet wells, channels, clarifiers, aeration basins, headworks structures and tank walls with light to moderate wastewater exposure | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1/4" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1/4"): Series N218 MortarClad — Applied at coverage rate Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 142 Epoxoline — 14.0–16.0 mils DFT | 18.0–22.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Elevated H2S / MIC, High-Build Epoxy Lining WW-C1.2 | Influent structures, wet wells, force-main discharge structures, headworks, enclosed channels, covered primary treatment structures, sludge holding/storage structures, other enclosed wastewater structures subject to elevated H₂S/MIC | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1"): Series N218 MortarClad — Applied at coverage rate Base Coat: Series G434 Perma-Shield H2S — 125 Glaze Coat: Series G435 Perma-Glaze — 15.0–20.0 mils DFT Note: Use Series G436 Perma-Shield FR for spray application of the base coat | 140.0–145.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate to Severe Deterioration / I&I, Structural Epoxy Lining (Epoxytec) WW-C1.3 | Deteriorated concrete manholes, wet wells, headworks, lift stations and structures with infiltration/inflow requiring a structural epoxy rehabilitation lining | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1/4" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1/4"): Series N218 MortarClad or Mortartec Ceramico — Applied at coverage rate Primer: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat (spray-applied): Series 456 CPP Sprayliner — 125–250 mils DFT Finish Coat (trowel-applied alternate): Series 454 CPP Trowel-Liner — 125–250 mils DFT | 129.0–256.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
WW-MDC1 — CONCRETE – ENCLOSED MESOPHILIC DIGESTERS | ||||
Exposed Concrete Walls and Floors, Medium Build WW-MDC1.1 | Exposed concrete walls, floors and beams inside enclosed mesophilic digesters — medium-build lining | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1"): Series N218 MortarClad — Applied at coverage rate Primer: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Finish Coat: Series 61 Tneme-Liner — 8.0–12.0 mils DFT | 12.0–18.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Underside of Digester Lid and Rim Skirt, High Build WW-MDC1.2 | Underside of concrete digester lids and rim skirts in mesophilic digesters — high-build lining | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1"): Series N218 MortarClad — Applied at coverage rate Primer: Series 61 Tneme-Liner — 4.0–6.0 mils DFT Finish Coat: Series G435 Perma-Glaze — 15.0–20.0 mils DFT | 19.0–26.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
WW-TDC1 — CONCRETE – ENCLOSED THERMOPHILIC DIGESTERS | ||||
Exposed Concrete Walls and Floors, Medium Build WW-TDC1.1 | Exposed concrete walls, floors and beams inside enclosed thermophilic digesters — mat-reinforced vinyl ester lining | SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater | Surfacer / Filler (1/4" and greater): Series 217 MortarCrete — Applied at coverage rate Surfacer / Filler (less than 1/4"): Series 215 Surfacing Epoxy — 25–40 SF/gal Primer: Series 1407 Vinester — 2.0–6.0 mils DFT First Coat: Series 1436 Vinester — 20.0–25.0 mils DFT Mat Reinforcement: Series 211-0227 1.5-oz Chopped Strand Mat — Embedded wet (not rated) Saturant: Series 1436 Vinester — 20.0–25.0 mils DFT Finish: Series 1436 Vinester — 20.0–25.0 mils DFT | 62.0–81.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
WW-C2 — SECONDARY CONTAINMENT (CHEMICAL-SPECIFIC) | ||||
Reinforced Novolac / Vinyl Ester Lining — Acid, Caustic, Oxidizer, Coagulant, Dechlorination, Organic WW-C2.1 | Concrete secondary containment areas, sumps and curbs at chemical storage and feed systems — acids, caustic, oxidizers (hypochlorite), coagulants, dechlorination and organic chemicals | SSPC-SP13/NACE No. 6, ICRI-CSP 3-5; clean and dry | Block Filler (CMU only): Series 130 Envirofill — 60–80 SF/gal Cant Cove: Trowelable lining at floor-to-wall transitions — Embedded wet (not rated) Primer: Series 201 Epoxoprime — 6.0–8.0 mils DFT Base Coat: Series 239SC ChemBloc — 8.0–12.0 mils DFT Reinforcement: 3/4-oz fiberglass mat — Embedded wet (not rated) Saturant: Series 239SC ChemBloc — 16.0–18.0 mils DFT Finish Coat: Series 282 Tneme-Glaze — 6.0–8.0 mils DFT | 36.0–46.0 mils DFT (over block filler applied at coverage rate) |
WW-S3 — CONDENSATION MITIGATION / THERMAL INSULATING COATING | ||||
Aerogel Insulative Coating on Steel Pipe, Tanks and Structure WW-S3.1 | Metal surfaces subject to surface condensation (chilled lines, damp/humid enclosed spaces) | SSPC-SP15 minimum (SSPC-SP6 preferred) | Primer: Series 394 PerimePrime — 2.5–3.5 mils DFT First Coat: Series 971 Aerolon — 40.0–50.0 mils DFT Intermediate: Series 971 Aerolon — 40.0–50.0 mils DFT Finish Coat: Series 971 Aerolon — 40.0–50.0 mils DFT Topcoat (exposed to view): Series 1028 Enduratone — 2.0–3.0 mils DFT | 124.5–156.5 mils DFT |
C1 — NEW OR PREVIOUSLY UNCOATED CMU | ||||
Moderate Duty, Water Based C1.2 | Interior concrete/CMU, new or unpainted, moderate/light service | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Block Filler: Series 130 Envirofill — 60–80 SF/gal First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT (over block filler applied at coverage rate) |
Moderate Duty, Solvent Based C1.3 | Mechanical/electrical rooms, workshops, garages, storage and service areas where a solvent-based epoxy finish is acceptable and low odor is not required | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Block Filler: Series 130 Envirofill — 60–80 SF/gal First Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT (over block filler applied at coverage rate) |
Moderate/Heavy Duty, Water Based w/ Urethane Finish C1.4 | Locker rooms, restrooms, kitchens, corridors, custodial and service areas needing a scrubbable, color-retentive urethane finish over low-odor epoxy | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Block Filler: Series 130 Envirofill — 60–80 SF/gal First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.0–9.0 mils DFT (over block filler applied at coverage rate) |
Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish C1.5 | Laboratories, kitchens, washdown rooms, corridors and high-abuse areas where a 100% solids epoxy build and urethane finish are required | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Block Filler: Series 1254 Epoxoblock WB — ~100 SF/gal (CMU) First Coat: Series 280 Tneme-Glaze — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.0–9.0 mils DFT (over block filler applied at coverage rate) |
Moderate/Heavy Duty, Chemical Resistant C1.6 | Chemical storage and feed rooms (non-immersion), laboratories, battery rooms, wash bays and areas subject to chemical splash or frequent washdown | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Block Filler: Series 130 Envirofill — 60–80 SF/gal First Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Finish Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT (over block filler applied at coverage rate) |
Heavy Duty / Washdown, 100% Solids Reinforced C1.7 | High-traffic corridors, secure or controlled-access areas, maintenance/service spaces, wet areas, laboratories and walls subject to repeated impact or abuse | Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust | Filler: Series 215 Surfacing Epoxy — 25–40 SF/gal Glass Mat: Series 273 ML Stranlok, embedded into wet Series 215 — Embedded wet Saturant: Series 280 Tneme-Glaze — 8.0–10.0 mils DFT Intermediate: Series 280 Tneme-Glaze — 6.0–8.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 16.0–21.0 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
C2 — NEW OR PREVIOUSLY UNCOATED CONCRETE | ||||
Moderate Duty, Water Based C2.2 | Basements, utility rooms, service corridors, mechanical rooms and general interior poured or precast concrete walls in occupied facilities | SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate Duty, Solvent Based C2.3 | Mechanical/electrical rooms, workshops, garages, service and process support areas with interior concrete walls where low odor is not required | SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, Water Based w/ Urethane Finish C2.4 | Locker rooms, restrooms, kitchens, corridors and frequently cleaned interior concrete walls needing a urethane finish | SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.7–10.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish C2.5 | Laboratories, washdown rooms, process support spaces and high-abuse interior concrete walls requiring a 100% solids epoxy build and urethane finish | SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 280 Tneme-Glaze — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.7–10.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, Chemical Resistant C2.6 | Chemical rooms (non-immersion), laboratories, wash bays and interior concrete walls subject to chemical splash or frequent washdown | SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Finish Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
C3 — EXISTING / PREVIOUSLY PAINTED CMU AND CONCRETE | ||||
Moderate Duty, Water Based C3.2 | Previously painted corridors, restrooms, break rooms, utility and service areas receiving a low-odor epoxy maintenance coating | SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate Duty, Solvent Based C3.3 | Previously painted mechanical rooms, workshops, garages and service areas where a solvent-based epoxy recoat is acceptable | SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, Water Based w/ Urethane Finish C3.4 | Previously painted locker rooms, restrooms, kitchens, corridors and frequently cleaned walls needing a urethane finish | SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 288/289 Enviro-Pox — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.7–10.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish C3.5 | Previously painted laboratories, washdown rooms and high-abuse walls requiring a 100% solids epoxy build and urethane finish | SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 280 Tneme-Glaze — 4.0–6.0 mils DFT Finish Coat: Series 297 Enviro-Glaze — 2.0–3.0 mils DFT | 6.7–10.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
Moderate/Heavy Duty, Chemical Resistant C3.6 | Previously painted chemical rooms (non-immersion), laboratories, wash bays and walls subject to chemical splash or washdown | SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT Filler (as needed): Series 215 Surfacing Epoxy — Applied at coverage rate First Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Finish Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT | 8.7–13.5 mils DFT (over surfacer/filler applied as needed — not a rated coat) |
C4 — CONCRETE CEILINGS – NEW, EXISTING PAINTED OR STRUCTURAL, PLANK AND DECK | ||||
Dry-Fall, High-Moisture / Natatorium Ceilings C4.1 | Pool or aquatic areas, high-humidity mechanical rooms, laundry areas, wash bays, wet-process rooms and persistently humid interior spaces | SSPC-SP13/NACE No. 6; clean and dry; remove loose/peeling coating on previously painted ceilings | Primer: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT Intermediate: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT Finish Coat: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT | 6.0–12.0 mils DFT |
Flexible / Mildew-Resistant Ceilings (Locker Rooms) C4.2 | Locker rooms, showers, laundry rooms, restrooms, wash areas and intermittently humid interior spaces | SSPC-SP13/NACE No. 6; clean and dry; remove loose/peeling coating on previously painted ceilings | Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT First Coat: Series 158 Bio-Lastic — 6.0–7.0 mils DFT Finish Coat: Series 158 Bio-Lastic — 6.0–7.0 mils DFT | 12.7–15.5 mils DFT |
S1 — NEW OR PREVIOUSLY UNCOATED STEEL | ||||
Moderate Duty, Solvent Based Epoxy S1.2 | Structural steel, columns, beams, equipment supports, platforms and miscellaneous steel in mechanical rooms, garages, shops and process support areas | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch-Up Primer: Series 1 Omnithane — 2.5–3.5 mils DFT First Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments. | 10.5–15.5 mils DFT (excludes touch-up coats) |
Moderate Duty, Solvent Based Epoxy w/ Urethane Finish S1.3 | Exposed structural steel, stairs, railings, mezzanines and equipment in lobbies, gymnasiums, corridors and other visible interior spaces needing color and gloss retention | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch-Up Primer: Series 1 Omnithane — 2.5–3.5 mils DFT First Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments. Note: Use Series 1090 as the finish coat for high traffic areas | 9.5–13.5 mils DFT (excludes touch-up coats) |
Heavy Duty, Chemical Resistant Epoxy S1.4 | Steel in chemical rooms, laboratories, wash bays and process areas subject to chemical splash, fumes or frequent washdown (non-immersion) | SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch-Up Primer: Series 1 Omnithane — 2.5–3.5 mils DFT First Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Stripe Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Finish Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT | 10.5–15.5 mils DFT (excludes stripe/touch-up coats) |
Overhead Structural Steel / Joists / Deck, Dry-Fall S1.5 | Overhead structural steel, bar joists, metal deck, ductwork and conduit in gymnasiums, warehouses, shops and open-ceiling spaces (dry-fall application) | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Primer: Series 1 Omnithane — 2.5–3.5 mils DFT Touch-Up Primer: Series 1 Omnithane — 2.5–3.5 mils DFT First Coat: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT Finish Coat: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments. | 6.5–11.5 mils DFT (excludes touch-up coats) |
Galvanized Steel, Epoxy Finish S1.6 | Galvanized substrates — interior, non-immersion | SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile | First Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
Galvanized Steel, Urethane Finish S1.7 | Galvanized substrates — interior, non-immersion, where a urethane finish is needed for color and gloss retention | SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile | First Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
Galvanized Steel, Light Architectural Duty S1.8 | Railings, stairs, ladders, supports, equipment frames, guards and miscellaneous galvanized or nonferrous metal | SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile | Primer: Series 116 Uni-Bond — 2.0–4.0 mils DFT Finish Coat: Series 1028 Enduratone — 2.0–3.0 mils DFT | 4.0–7.0 mils DFT |
S2 — EXISTING / PREVIOUSLY PAINTED STEEL | ||||
Moderate Duty, Solvent Based Epoxy Finish S2.2 | Previously painted structural steel, equipment supports, platforms and miscellaneous steel in mechanical rooms, garages, shops and process support areas | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges | Spot Prime: Series 135 Chembuild — 4.0–6.0 mils DFT First Coat: Series 135 Chembuild — 4.0–6.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT (excludes spot-prime coats) |
Moderate Duty, Solvent Based Epoxy w/ Urethane Finish S2.3 | Previously painted exposed steel, stairs, railings and equipment in visible interior spaces needing color and gloss retention | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges | Spot Prime: Series 135 Chembuild — 4.0–6.0 mils DFT First Coat: Series 135 Chembuild — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Note: Use Series 1090 as the finish coat for high traffic areas | 7.0–10.0 mils DFT (excludes spot-prime coats) |
Heavy Duty, Chemical Resistant Epoxy S2.4 | Previously painted steel in chemical rooms, laboratories, wash bays and process areas subject to chemical splash or washdown (non-immersion) | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning; SSPC-SP11 to bare metal at corroded areas; feather transition edges | Touch-Up Primer: Series 1 Omnithane — 2.5–3.5 mils DFT First Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT Finish Coat: Series 104 H.S. Epoxy — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT (excludes touch-up coats) |
Overhead Structural Steel / Joists / Deck, Dry-Fall S2.5 | Previously painted overhead structural steel, joists, deck, ductwork and conduit in open-ceiling spaces (dry-fall application) | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges | Spot Prime: Series 135 Chembuild — 4.0–6.0 mils DFT First Coat: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT Finish Coat: Series 115 Uni-Bond DF — 2.0–4.0 mils DFT | 8.0–14.0 mils DFT |
Galvanized Steel, Epoxy Finish S2.6 | Galvanized substrates — interior, non-immersion | SSPC-SP1; SSPC-SP2/SP3 to degloss and remove loose coating; SSPC-SP16 at exposed galvanizing | First Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Finish Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
Galvanized Steel, Urethane Finish S2.7 | Previously coated galvanized substrates — interior, non-immersion, where a urethane finish is needed for color and gloss retention | SSPC-SP1; SSPC-SP2/SP3 to degloss and remove loose coating; SSPC-SP16 at exposed galvanizing | First Coat: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
Hollow Metal Doors, Frames, Railings — Moderate/Heavy Duty S2.9 | Lobbies, atriums, public areas, assembly spaces, garages, maintenance areas, exposed columns/beams and existing mechanical or support steel | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges | Primer: Series 27 Typoxy — 3.0–4.0 mils DFT Finish Coat: Series 1090 Endura-Shield — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
M1 — MISCELLANEOUS INTERIOR SUBSTRATES | ||||
PVC Pipe, Trim and Plastic Components M1.2 | PVC trim, piping, panels and miscellaneous plastic components requiring field coating | Solvent clean and dry; lightly sand with #150-200 sandpaper | First Coat: Series 1028/1029 Enduratone — 2.0–3.0 mils DFT Finish Coat: Series 1028/1029 Enduratone — 2.0–3.0 mils DFT | 4.0–6.0 mils DFT |
Insulated Pipe Jacketing (Canvas / PVC Jacket) M1.3 | Interior insulated pipe (jacketing) | Clean and dry | First Coat: Series 1026 Enduratone — 2.0–3.0 mils DFT Finish Coat: Series 1026 Enduratone — 2.0–3.0 mils DFT | 4.0–6.0 mils DFT |
Interior Aluminum and Non-Ferrous Metal M1.4 | Railings, stairs, ladders, supports, equipment frames, guards and miscellaneous galvanized or nonferrous metal | SSPC-SP1; light abrasive sweep blast or uniformly sand to profile; avoid damaging/warping thin components | Primer: Series 116 Uni-Bond — 2.0–4.0 mils DFT Finish Coat: Series 1028/1029 Enduratone — 2.0–3.0 mils DFT | 4.0–7.0 mils DFT |
EC1 — NEW OR PREVIOUSLY UNCOATED CMU AND CONCRETE | ||||
Elastomeric / Crack-Bridging, Smooth Finish EC1.1 | Exterior masonry/CMU, unpainted | SSPC-SP13/NACE No. 6; clean, dry, free of oil/grease/form-release agents; allow new concrete/CMU to cure min. 14 days; repair cracks per mfr procedure | Block Filler (CMU, as needed): Series 130 Envirofill — 60–80 SF/gal Primer: Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT First Coat: Series 156 Enviro-Crete — 6.0–8.0 mils DFT Finish Coat: Series 156 Enviro-Crete — 6.0–8.0 mils DFT | 12.7–17.5 mils DFT (over block filler applied at coverage rate) |
EC2 — EXISTING / PREVIOUSLY PAINTED CMU, BRICK AND CONCRETE | ||||
Elastomeric / Crack-Bridging Recoat EC2.1 | Exterior masonry/CMU, previously painted | Power wash; remove loose/peeling coating and chalk; clean and dry | Primer (as needed): Series 151-1051 Elasto-Grip FC — 0.7–1.5 mils DFT First Coat: Series 156 Enviro-Crete — 4.0–6.0 mils DFT Finish Coat: Series 156 Enviro-Crete — 4.0–6.0 mils DFT | 8.0–12.0 mils DFT; optional Primer (as needed) 0.7–1.5 |
ES1 — NEW OR FULL-COATING-REMOVAL STEEL | ||||
Zinc / Epoxy / Urethane (Good) ES1.1 | New fabrication or full coating removal — exterior structural steel, tanks, pipe supports and equipment, non-immersion service | SSPC-SP6/NACE No. 3 Commercial Blast Cleaning | Shop or Field Primer: Series 90-97 Tneme-Zinc — 2.5–3.5 mils DFT Touch-Up Primer: Series 90G-1K97 Tneme-Zinc — 2.5–3.5 mils DFT Intermediate: Series V69 Hi-Build Epoxoline II — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Note: Use Series 1090 as the finish coat for high traffic areas | 9.5–13.5 mils DFT (excludes touch-up coats) |
ES2 — EXISTING / PREVIOUSLY PAINTED STEEL (OVERCOAT) | ||||
Epoxy Mastic / Urethane (Good) ES2.1 | Existing exterior steel with a sound coating — support steel, equipment, enclosures, fencing, gates, tank exteriors and miscellaneous steel receiving an overcoat | SSPC-SP2/SP3 Hand/Power Tool Cleaning; remove loose coating; feather transition edges | Spot Prime: Series 135 Chembuild — 4.0–6.0 mils DFT Full Prime Coat: Series 135 Chembuild — 4.0–6.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Note: Use Series 1090 as the finish coat for high traffic areas | 7.0–10.0 mils DFT (excludes spot-prime coats) |
ES3 — GALVANIZED STEEL | ||||
New or Full Coating Removal, Urethane Finish (Good) ES3.1 | New or stripped exterior galvanized railings, ladders, fencing, gates, support poles, pipe supports and miscellaneous galvanized metal | SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile | Primer: Series V69 Hi-Build Epoxoline II — 3.0–4.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT | 6.0–8.0 mils DFT |
Previously Coated Galvanized, Overcoat ES3.3 | Previously coated exterior galvanized railings, ladders, doors and frames, fencing, gates, support poles and miscellaneous galvanized metal | Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges | Spot / Prime Coat: Series 27 Typoxy — 3.0–4.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Optional Finish: Series 1070V Fluoronar — 2.0–3.0 mils DFT | 6.0–8.0 mils DFT; Optional Finish 2.0–3.0 |
ES4 — ALUMINUM AND NON-FERROUS METAL | ||||
General ES4.1 | Louvers, screens, railings, architectural trim, frames, stairs/platforms and exposed aluminum components | Light abrasive sweep blast (SSPC-SP16), uniform angular profile 1.0-2.0 mils; avoid damaging/warping thin components | Primer: Series V69 Hi-Build Epoxoline II — 2.0–3.0 mils DFT Intermediate: Series 1095 Endura-Shield — 2.0–3.0 mils DFT Finish Coat: Series 1071 Fluoronar — 2.0–3.0 mils DFT | 6.0–9.0 mils DFT |
ES5 — HOLLOW METAL DOORS AND FRAMES | ||||
Hollow Metal Doors, Frames, Railings — Moderate/Heavy Duty ES5.2 | Hollow-metal doors, frames, access doors, service doors, overhead-door components and similar ferrous assemblies | Uniformly scarify to remove glaze/sheen (test patch required) | Primer: Series 27 Typoxy — 3.0–4.0 mils DFT Finish Coat: Series 1095 Endura-Shield — 3.0–4.0 mils DFT Note: Use Series 1090 as the finish coat for high traffic areas | 6.0–8.0 mils DFT |
EW1 — WOOD | ||||
Bare or Previously Painted EW1.1 | Doors, trim, millwork, paneling and exposed architectural wood | Clean and dry; sand smooth | Primer: Series V10 Tnemec Primer — 2.0–3.5 mils DFT First Coat: Series 1028 Enduratone — 2.0–3.0 mils DFT Finish Coat: Series 1028 Enduratone — 2.0–3.0 mils DFT | 6.0–9.5 mils DFT |
ESL1 — WATER REPELLENTS, SEALERS AND ANTI-GRAFFITI | ||||
Penetrating Silane/Siloxane Water Repellent ESL1.1 | Exterior concrete, precast, brick, block, stone, stucco and other absorptive masonry exposed to weather; clear penetrating water repellent with no film build | Per product surface-absorption test; clean, dry, free of efflorescence | Sealer: Series 633 Prime-A-Pell H2O (Tnemec) — or Tex-Cote Rainstopper 120/140 — N/A (penetrating sealer) | Not applicable — penetrating sealer, no measurable dry film thickness |
E1 — 100% SOLIDS EPOXY SYSTEMS | ||||
1/16" Solid Color Epoxy Broadcast — Light Duty E1.3 | Public restrooms, locker/shower dry areas, stairwells, and other light/moderate-duty areas where a decorative finish is desired | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 3 minimum | Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Primer: Series N222 Deco-Tread — 250–320 SF/gal Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand — 80–100 SF/gal Grout Coat: Series N222 Deco-Tread (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/16" system |
1/8" Solid Color Epoxy Broadcast — Moderate Duty E1.4 | Public restrooms, locker/shower dry areas, stairwells, and other light/moderate-duty areas where a decorative finish is desired | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 3 minimum | Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Primer: Series N222 Deco-Tread — 250–320 SF/gal First Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand — 80–100 SF/gal Second Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand — 80–100 SF/gal Grout Coat: Series N222 Deco-Tread (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/8" system |
WB1 — WATER-BASED EPOXY | ||||
1/16" Solid Color Epoxy Broadcast — Light Duty WB1.3 | Offices, administrative areas, low-traffic corridors, break rooms, multipurpose rooms and dry storage areas in occupied buildings or where low-odor application is required | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 2-3 minimum | Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Primer: Series 288/289 Enviro-Pox — 250–320 SF/gal Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand — 80–100 SF/gal Grout Coat: Series 288/289 Enviro-Pox (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/16" system |
1/8" Solid Color Epoxy Broadcast — Moderate Duty WB1.4 | Corridors, common areas, break and dining areas, equipment rooms, storage and service areas in occupied buildings or where low-odor application is required | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 2-3 minimum | Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Primer: Series 288/289 Enviro-Pox — 250–320 SF/gal First Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand — 80–100 SF/gal Second Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand — 80–100 SF/gal Grout Coat: Series 288/289 Enviro-Pox (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/8" system |
UC1 — URETHANE CEMENT SYSTEMS | ||||
1/4" Solid Color Urethane Cement — Heavy Duty UC1.1 | Mechanical rooms, blower buildings, maintenance shops, and loading/receiving areas — heavy-duty interior floor areas subject to thermal shock, mechanical abuse, or frequent washdown | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 5 minimum | Base / Broadcast Coat: Series N242 Ultra-Tread S with 30/50 aggregate — 37 SF/kit Coving (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Grout Coat: Series N222 Deco-Tread (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/4" system |
1/8" Solid Color Urethane Cement — Moderate/Heavy Duty UC1.3 | Below-grade pump station dry pits, piping galleries/tunnels, and other moderate/heavy-duty floor areas with elevated moisture vapor transmission (MVT) concerns | NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 5 minimum | Coving (where required): Series N283, N222 or 288 epoxy with aggregate — Applied at coverage rate Base / Broadcast Coat: Series N241 Ultra-Tread MVT with aggregate — 90 SF/kit Grout Coat: Series N222 Deco-Tread (pigmented) — 160–200 SF/gal Finish Coat: Series 248 Everthane with 821 Field Colorant — 500–600 SF/gal | Nominal 1/8" system |
Where to Go Next
For CSI 3-part bid/construction language: Section 09 96 23, High-Performance Coatings and Linings (Wastewater Treatment), or contact Atlantic Coating Consultants.
For the full architectural interior/exterior system set: Section 09 96 00, High-Performance Coatings, and the companion Architectural Short-Form System Reference Guide; for floors, Section 09 67 23 and the Resinous Flooring guide.
For unlisted chemicals, conditions, substrates, or flooring requirements: contact Atlantic Coating Consultants.
Atlantic Coating Consultants | Wally Bates | atlantic@tnemec.com | 484-644-5303