Guide Specification: Section 09 96 24 High-Performance Coatings, Water Treatment
This is ACC's guide specification for water treatment plants, including potable water immersion, written in CSI 3-part format with Tnemec Company as the basis of design. The full text is below. Edit it to suit your project, or ask us to tailor it for you.
Editable Word file: get the Word version. We ask for your name and email.
Quick system selection: see the companion short-form system reference guide.
Specification for your project: ask ACC to tailor this section.
Questions: atlantic@tnemec.com or 484-644-5303.
SECTION 09 96 24 — HIGH-PERFORMANCE COATINGS AND LININGS
Guide Specification — Water Treatment Facilities
Specifier Note: This guide specification is provided as a technical resource by Atlantic Coating Consultants (ACC), an independent representative for Tnemec, TEX-COTE and Epoxytec, and is compiled from ACC's standard Tnemec coating systems. It is a template for water treatment plants, potable water storage tanks, pump stations, clearwells and distribution-system structures and is not a project-specific specification. The Coating System Schedule lists the potable-water immersion (NSF/ANSI/CAN 61 and 600) and tank-exterior systems first, followed by the shared interior, exterior and flooring systems that also appear in the Architectural (09 96 00) and Resinous Flooring (09 67 23) guides. Each system is identified by its System Code. Select the systems required, add typical locations for the facility, and delete the remainder along with all Specifier Notes. VERIFY ALL PRODUCT DESIGNATIONS, COATS, DRY FILM THICKNESSES AND SURFACE PREPARATION REQUIREMENTS WITH ATLANTIC COATING CONSULTANTS OR TNEMEC COMPANY BEFORE ISSUING FOR BID OR CONSTRUCTION. Contact: Wally Bates, Atlantic Coating Consultants — atlantic@tnemec.com — 484-644-5303.
This product selection guide is written according to the Construction Specifications Institute (CSI) Format. This specification is only a guide listing various coating system options and should not be used as a final specification. Tnemec Company, Inc. is not liable in any way for revisions to, or use of, this product guide specification by any end user. A qualified design professional should review and edit this document to suit project requirements and coordinate this Section with other specification sections and the drawings. This Section uses the term "Engineer"; change this term throughout to match the term used to identify the design professional as defined in the General and Supplementary Conditions.
PART 1 — GENERAL
1.1 SCOPE
A. This Section includes shop and field surface preparation and shop and field application of high-performance coatings and linings related to water treatment facilities and potable water storage tanks.
B. Surface preparation, including in the shop and applications of metal primer, and field applications of primers, intermediate coats and finishes, are specified in this Section.
C. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
D. Related Sections:
1. Section 03 30 00 — Cast-in-Place Concrete.
2. Section 04 20 00 — Unit Masonry.
3. Section 05 12 00 — Structural Steel Framing.
4. Section 09 67 23 — Resinous Flooring.
5. Section 09 96 00 — High-Performance Coatings (Architectural), for administration and non-process buildings.
6. Section 33 16 00 — Water Utility Storage Tanks (where issued separately).
7. Section 46 00 00 — Water and Wastewater Equipment.
1.2 REFERENCES
A. This Section contains references to the governing standards and documents listed below. They are a part of this Section as specified and modified; the current version shall apply unless otherwise noted. In case of conflict between the requirements of this Section and those of the listed documents, the more stringent of the requirements shall prevail.
B. American Water Works Association (AWWA):
1. ANSI/AWWA D102 — Coating Steel Water-Storage Tanks.
2. ANSI/AWWA C652 — Disinfection of Water-Storage Facilities.
3. ANSI/AWWA C651 — Disinfecting Water Mains.
C. NSF International:
1. NSF/ANSI/CAN 61 — Drinking Water System Components — Health Effects.
2. NSF/ANSI/CAN 600 — Health Effects Evaluation and Criteria for Chemicals in Drinking Water.
D. SSPC: The Society for Protective Coatings / AMPP:
1. SSPC-SP1 — Solvent Cleaning.
2. SSPC-SP2 — Hand Tool Cleaning.
3. SSPC-SP3 — Power Tool Cleaning.
4. SSPC-SP6 / NACE No. 3 — Commercial Blast Cleaning.
5. SSPC-SP10 / NACE No. 2 — Near-White Metal Blast Cleaning.
6. SSPC-SP11 — Power Tool Cleaning to Bare Metal.
7. SSPC-SP13 / NACE No. 6 — Surface Preparation of Concrete.
8. SSPC-SP15 — Commercial Grade Power Tool Cleaning.
9. SSPC-SP16 — Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals.
10. SSPC-Paint 20 — Zinc-Rich Coating.
11. SSPC-Paint 22 — Epoxy Polyamide Paints.
12. SSPC-Paint 36 — Two-Component Weatherable Aliphatic Polyurethane Topcoat.
13. SSPC-PA 2 — Procedure for Determining Conformance to Dry Coating Thickness Requirements.
E. AMPP (formerly NACE International and SSPC):
1. NACE SP0274 — High-Voltage Electrical Inspection of Pipeline Coatings.
2. AMPP SP0188 — Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates.
3. AMPP SP0892 — Coatings and Linings over Concrete for Chemical Immersion and Containment Service.
F. National Association of Pipe Fabricators (NAPF):
1. NAPF 500-03 — Surface Preparation Standard for Ductile Iron Pipe and Fittings Receiving Special External Coatings and/or Special Internal Linings.
G. American Concrete Institute (ACI):
1. ACI 224.1R — Causes, Evaluation and Repair of Cracks in Concrete Structures.
2. ACI 301 — Specifications for Structural Concrete.
3. ACI 308R — Guide to Curing Concrete.
4. ACI 350 — Code Requirements for Environmental Engineering Concrete Structures.
5. ACI 515.2R — Guide to Selecting Protective Treatments for Concrete.
6. ACI 546R — Concrete Repair Guide.
7. ACI 546.3R — Guide for the Selection of Materials for the Repair of Concrete.
H. ASTM International (ASTM):
1. ASTM C413 — Absorption of Chemical-Resistant Mortars, Grouts, Monolithic Surfacings, and Polymer Concretes.
2. ASTM C868 — Chemical Resistance of Protective Linings.
3. ASTM D870 — Testing Water Resistance of Coatings Using Water Immersion.
4. ASTM D1653 — Water Vapor Transmission of Organic Coating Films.
5. ASTM D2240 — Rubber Property — Durometer Hardness.
6. ASTM D4060 — Abrasion Resistance of Organic Coatings by the Taber Abraser.
7. ASTM D4263 — Indicating Moisture in Concrete by the Plastic Sheet Method.
8. ASTM D4417 — Field Measurement of Surface Profile of Blast Cleaned Steel.
9. ASTM D4541 — Pull-Off Strength of Coatings Using Portable Adhesion Testers.
10. ASTM D6386 — Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting.
11. ASTM F1869 — Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride.
I. International Concrete Repair Institute (ICRI):
1. ICRI Guideline No. 310.1R — Surface Preparation for the Repair of Deteriorated Concrete Resulting from Reinforcing Steel Corrosion.
2. ICRI Guideline No. 310.2R — Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays.
1.3 SUMMARY
A. This Section includes surface preparation, priming, coating, lining, and finishing of the following surfaces, in immersion and non-immersion service:
1. Steel and Ductile Iron — structural steel, tanks, equipment, pipe, valves and fittings (new and existing).
2. Steel Potable Water Storage Tanks — interior wetted surfaces (NSF/ANSI/CAN 61 and 600 certified linings) and exterior surfaces.
3. Concrete — potable water immersion (clearwells, reservoirs, filter and contact basins) and non-immersion process areas.
4. Secondary Containment — chemical-specific reinforced linings.
5. Condensation Mitigation — insulative coating on cold-service pipe, tanks and structure.
6. Shared interior and exterior systems — CMU and concrete walls, non-immersion steel, galvanized steel, aluminum, hollow metal, PVC, insulated pipe jacketing and resinous floors.
B. Coat exposed surfaces whether or not colors are designated in schedules, except where a surface or material is specifically indicated not to be coated or is to remain natural. Where an item or surface is not specifically mentioned, coat the same as similar adjacent materials or surfaces. If color or finish is not designated, the Engineer will select from standard colors or finishes available.
C. Coating includes field-coating exposed bare and covered pipes and ducts (including color coding), hangers, exposed steel and iron work, and primed metal surfaces of mechanical and electrical equipment.
1.4 SUBMITTALS
A. Product Data:
1. Submit manufacturer's product literature describing products to be provided, giving manufacturer's name, product name, and product line number for each material.
2. Submit technical data sheets for each coating, giving descriptive data, curing times, mixing, thinning, and application requirements.
3. Provide material analysis, including vehicle type and percentage by weight and by volume of vehicle, resin and pigment.
4. Submit manufacturer's Safety Data Sheets (SDS) and other safety requirements.
5. Submit current NSF/ANSI/CAN 61 and NSF/ANSI/CAN 600 listings for each coating or lining scheduled for potable water immersion service, showing the product, the tank or pipe size range and the service for which it is listed.
B. Shop Drawings:
1. Submit a complete list of products proposed for use, including identifying product names and catalog numbers.
2. Arrange in same format as the Coating System Schedule below.
3. Include applicable manufacturer's data and recommendations.
C. Samples:
1. Submit color charts displaying manufacturer's full range of standard colors for initial selection by Engineer.
1.5 QUALITY ASSURANCE
A. Manufacturer's Quality Assurance:
1. Provide products from a company specializing in manufacture of high-performance coatings with a minimum of 10 years' experience.
B. Applicator Quality Assurance:
1. Applicator shall be trained in application techniques and procedures of coating materials and shall demonstrate a minimum of 5 years successful experience in such application.
2. Submit list of a minimum 5 completed projects of similar size and complexity to this work. Include for each project:
a. Project name and location.
b. Name of owner.
c. Name of contractor.
d. Name of engineer.
e. Name of coating manufacturer.
f. Approximate area of coatings applied.
g. Date of completion.
3. Maintain, throughout the duration of application, a crew of applicators who are fully qualified to satisfy specified qualifications.
C. Single Source Responsibility:
1. Materials shall be products of a single manufacturer or items standard with manufacturer of specified coating materials.
2. Provide secondary materials which are produced or are specifically recommended by the coating system manufacturer to ensure compatibility of the system.
D. Regulatory Requirements:
1. Conform to applicable codes and ordinances for flame, fuel, smoke, and volatile organic compound (VOC) ratings requirements for finishes at time of application.
E. Pre-Installation Meetings:
1. Schedule a conference and inspection to be held on-site before field application of coating systems begins.
2. Conference shall be attended by Contractor, Owner's representative, Engineer, coating applicators, and a representative of the coating material manufacturer.
3. Topics to be discussed at the meeting shall include:
a. A review of Contract Documents and accepted shop drawings; deviations or differences shall be resolved.
b. Environmental conditions, surface conditions, surface preparation, application procedures, and protection following application.
c. Areas on-site available for use as storage and working areas.
d. Confined-space entry, ventilation and dehumidification requirements for immersion linings.
4. Prepare and submit, to parties in attendance, a written report of the pre-installation conference within 3 days following the conference.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Packing, Shipping, Handling, and Unloading:
1. Deliver products in manufacturer's original unopened containers. Each container shall have manufacturer's label, intact and legible, fully identifying brand, type, grade, class, and other qualifying information used to describe contents.
2. Include on label for each container:
a. Manufacturer's name.
b. Type of coating.
c. Manufacturer's stock number.
d. Color name and number.
e. Instructions for thinning, where applicable.
B. Storage and Protection:
1. Store materials in a protected area, away from construction activities. Restrict storage area to coating materials and related equipment.
2. Maintain temperature in area of storage between 40 degrees F and 110 degrees F.
3. Comply with health and fire safety regulations.
4. Remove damaged materials from Site.
1.7 PROJECT CONDITIONS
A. Environmental Requirements — apply coating materials under conditions as follows:
1. Air temperature shall not be below 35 degrees F or above 110 degrees F, unless the product data sheet requires otherwise.
2. Refer to specific product data sheets for minimum surface temperature requirements. Surface temperatures shall be at least 5 degrees F above the dew point and in a rising mode.
3. Relative humidity shall be no higher than 85 percent.
4. For exterior spray application, wind velocity shall be less than 15 mph.
5. Atmosphere shall be relatively free of airborne dust.
6. Provide dehumidification and ventilation in tanks, clearwells and enclosed structures as required to maintain the above conditions through cure.
1.8 SEQUENCING
A. Coordination:
1. Perform work in proper sequence with work of other trades to avoid damage to finished work.
2. Where coatings are scheduled to be applied over shop-applied coatings, coordinate work of such shop-applied products to ensure compatibility with field-applied coating systems.
PART 2 — PRODUCTS
2.1 BASIS OF DESIGN MANUFACTURER
A. Products specified are manufactured by Tnemec Company, Inc., 123 West 23rd Ave, North Kansas City, MO 64116, (816) 483-3400, www.tnemec.com, and are specified as a standard of quality/performance and basis of design. The specified basis of design is intended to provide the longest service life, lowest life cycle cost, and most sustainable solution.
B. Contact: Wally Bates, Atlantic Coating Consultants — atlantic@tnemec.com — 484-644-5303.
C. Materials specified herein shall not preclude consideration of equivalent or superior materials. Submitted equivalent materials or other substitutions shall be submitted to the specifier for consideration in compliance with substitution procedures in Division 01 of the Project Manual and include the following:
1. Requests for substitution shall be provided no later than fourteen (14) days prior to the published bid opening date and must include all required data as listed in these specifications. Substitution requests with incomplete data shall not be reviewed.
2. Requests for substitution shall be made by a plan-holding, licensed, prospective bidder on the project.
3. Requests for substitution shall include actual case histories as evidence of satisfactory past performance in a similar environment with similar estimated service life of the system specified.
4. Substitutions will not be considered that change the generic type or number of coats, or do not meet specified dry film thicknesses.
5. Requests for substitution shall include manufacturer's certified test reports showing the substitute product's full list of performance data for comparison.
6. After the second submittal, Engineer/Owner or Owner's Agent hourly rates will be charged to review further submittals.
D. Bidders desiring to use coatings other than those specified shall submit those with their proposal based on the specified materials, and indicate the sum which will be added to or deducted from the base bid should alternate materials be accepted.
2.2 PRODUCTS — GENERAL
A. Provide shop and field primers, intermediate coats, linings and finish coats from a single manufacturer that are compatible with one another and with the substrates indicated, under the conditions of service and application.
B. Provide secondary materials (thinners, cleaners, surfacers, repair mortars, reinforcing mat and cove materials) that are produced or specifically recommended by the coating system manufacturer.
C. Generic coating types, NSF status and typical DFT of each product scheduled herein are listed on the Tnemec product data sheets.
D. Coatings and linings in contact with potable water shall be certified to NSF/ANSI/CAN 61 and NSF/ANSI/CAN 600 for the tank or pipe size and the service intended, and shall be applied and cured within the limits of the listing.
PART 3 — EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions under which coating will be performed for compliance with application requirements. Surfaces receiving coatings must be thoroughly dry before coating is applied.
B. Do not begin to apply coatings until unsatisfactory conditions have been corrected.
C. Start of coating will be construed as the Applicator's acceptance of surfaces and conditions within a particular area.
D. Coordination of Work: Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers.
E. Notify the Engineer about anticipated problems using the materials specified over substrates primed by others.
3.2 PREPARATION
A. General: Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be coated, or provide surface-applied protection prior to surface preparation and coating. Following completion of coating operations in each space or area, have items reinstalled by workers skilled in the trades involved.
B. Cleaning: Before applying coatings or other surface treatments, clean the substrates of substances that could impair the bond of the various coatings. Remove oil and grease prior to cleaning. Schedule cleaning and coating so dust and other contaminants from the cleaning process will not fall on wet, newly coated surfaces.
C. Surface Preparation: Clean and prepare surfaces to be coated according to the manufacturer's instructions for each particular substrate condition, the preparation scheduled for each system in the Coating System Schedule, and as specified below.
D. Ferrous Metal Surfaces:
1. Surfaces shall be free of residual deposits of grease, rust, scale, dirt, dust, and oil.
2. Immersion Service:
a. Prepare substrate in accordance with SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning, including removal of shop primer where scheduled.
b. Provide an angular surface profile in accordance with the manufacturer's product data sheet for the lining scheduled; consult the manufacturer's technical service for high-build systems.
3. Non-Immersion, Interior and Exterior Exposed:
a. SSPC-SP6/NACE No. 3 Commercial Blast Cleaning. If abrasive blasting is deemed impractical, clean surfaces per SSPC-SP15 Commercial Grade Power Tool Cleaning. Feather edges to make touch-up patches inconspicuous. Field welds and touch-ups shall be prepared to conform to original surface preparation standards as indicated in the Coating System Schedule.
b. Shop-applied prime coatings damaged during transportation, construction or installation shall be thoroughly cleaned and touched up in the field using repair procedures which ensure complete protection of adjacent primer. Repair methods may include wire brushing, hand or power tool cleaning or dry abrasive blast cleaning; to prevent injury to surrounding coated areas, blast cleaning may necessitate use of lower air pressure, small nozzle and abrasive particle sizes, short blast nozzle distance from surface, shielding and masking.
c. Existing coated steel scheduled for overcoat: wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss and remove loose coating; SSPC-SP11 to bare metal at corroded areas; feather transition edges.
E. Cast and Ductile Iron, including Mill-Coated Ductile Iron (Immersion Service):
1. Solvent Cleaning: All surfaces shall first be inspected and pre-cleaned with the appropriate solvents to remove grease, oil and other soluble contaminants, preferably by scrubbing with a stiff bristle brush soaked in solvent. Prior to evaporation remove solvent by wiping with clean, lint-free rags. Remove rag residue with dry, oil-free compressed air.
2. Reference NAPF 500-03, Surface Preparation Standard for Ductile Iron Pipe and Fittings Receiving Special External Coatings and/or Special Internal Linings.
3. Surface Profile: Measure surface profile (anchor pattern) in accordance with ASTM D4417, Method C.
a. If the surface profile is less than that required by the manufacturer, proceed with brush-off blast cleaning per NAPF 500-03-04.
b. If the surface profile meets the manufacturer's recommendation, proceed with hand or power tool cleaning per NAPF 500-03-03. Consult the manufacturer's technical service for high-build coating systems.
4. Brush-Off Blast Cleaning (NAPF 500-03-04): Remove all loose annealing oxides, loose rust, dirt, and other foreign matter by compressed-air nozzle abrasive blast cleaning using a fine-grade abrasive. Remove remaining dust with dry, oil-free compressed air or vacuum. Recheck surface profile prior to coating.
5. Hand or Power Tool Cleaning (NAPF 500-03-03): Remove all loose annealing oxides, loose rust, dirt, and other foreign matter with hand or power tools. Do not use tools that burnish or smooth the natural roughness of the cast surface. Remove remaining dust with dry, oil-free compressed air or vacuum.
6. Protection from Moisture: Cleaned cast iron surfaces shall be protected from high humidity, rainfall, and surface moisture. All surfaces shall be clean, dry and at least 5 degrees F above the dew point during application of protective coatings.
F. Galvanized Steel, Aluminum, and Other Non-Ferrous Metals (Immersion and Non-Immersion):
1. SSPC-SP16 Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals, in accordance with ASTM D6386: uniformly abrade the galvanized or aluminum surface without damaging the substrate.
G. Stainless Steel and Copper Surfaces:
1. Stainless Steel (Immersion and Non-Immersion): Provide uniform scarification per SSPC-SP16 Abrasive Brush-Off Blast Cleaning or power grinding.
2. Copper: SSPC-SP1 Solvent Cleaning, followed by uniform scarification with 80-grit aluminum oxide sandpaper.
H. Cast-in-Place and Precast Concrete Surfaces — Non-Immersion:
1. All specified surface preparation shall be performed in accordance with the latest version of SSPC-SP13/NACE No. 6 and ICRI Guideline 310.2R and other standards referenced in this Section.
2. Allow concrete to cure 28 days. Verify dryness by testing for moisture with a plastic-sheet test per ASTM D4263.
3. Abrasive blast clean or mechanically grind concrete per SSPC-SP13/NACE No. 6 to remove laitance, form coatings and contaminants and to provide a uniform surface texture at the ICRI-CSP profile listed on the manufacturer product data sheet.
4. Perform blast cleaning to open voids and bug holes so that holes are concave; keep aggregate exposure to a minimum.
5. Fill voids, bug holes and cavities from 1/8 inch to 1 inch flush with the surface using Tnemec Series N218 MortarClad; fill deeper cavities from 1 inch to 4 inches using Tnemec Series 217 MortarCrete.
6. Follow preparation with vacuum cleaning to remove all dust, dirt or friable substances, leaving clean, dust-free surfaces.
I. Concrete — Immersion Service:
1. All specified surface preparation shall be performed in accordance with the latest version of the SSPC, NACE, ICRI and other standards referenced in this Section.
2. Allow concrete to cure 28 days. Verify dryness by plastic-sheet test per ASTM D4263; for horizontal surfaces, if necessary, perform ASTM F1869 calcium chloride testing. Moisture vapor emission shall not exceed three pounds per 1,000 square feet in 24 hours.
3. Remove oil and grease before mechanical cleaning using an alkaline-based emulsifying detergent recommended by the resurfacing material manufacturer.
4. Where mechanical cleaning is accomplished by blast cleaning, the abrasive used shall be washed, graded and free of contaminants that might interfere with the adhesion of the resurfacing materials.
5. Reference SSPC-SP13/NACE No. 6 and ICRI Guideline 310.2R:
a. Specific Concrete Surface Profile (CSP) to be determined by the condition of the concrete and the lining scheduled; CSP 5 or greater for high-build linings unless otherwise scheduled.
b. Clean the entire surface to remove laitance, form coatings, and provide a uniform surface texture.
c. Perform blast cleaning to open voids and bug holes so that holes are concave; keep aggregate exposure to a minimum. Resurface voids, bug holes and cavities from 1/8 inch to 1 inch using Tnemec Series N218 MortarClad; fill deeper cavities from 1 inch to 4 inches flush with the surface using Tnemec Series 217 MortarCrete.
d. Follow preparation with vacuum cleaning to remove all dust, dirt or friable substances, leaving clean, dust-free surfaces for resurfacing.
6. Severely deteriorated concrete (exposed aggregate, loss of section): remove all unsound concrete to sound substrate per ICRI 310.1R before resurfacing; the Engineer shall confirm structural adequacy before lining.
J. Concrete Floors — Resinous Flooring Systems:
1. All specified surface preparation shall be performed in accordance with SSPC-SP13/NACE No. 6 and ICRI Guideline 310.2R.
2. Allow concrete to cure 28 days. Verify dryness per ASTM D4263 and, for horizontal surfaces, ASTM F1869; moisture vapor emission shall not exceed three pounds per 1,000 square feet in 24 hours, or the limit on the product data sheet for the system scheduled.
3. Remove oil and grease before mechanical cleaning using an alkaline-based emulsifying detergent recommended by the manufacturer.
4. Shot blast or mechanically abrade to remove laitance, curing compounds, hardeners, sealers and other contaminants and to provide the ICRI-CSP surface profile scheduled for the system.
5. Fill large voids and other cavities with the recommended filler or surfacer.
K. Masonry Surfaces (facing brick or concrete masonry units):
1. Allow surfaces to cure for not less than 30 days prior to coating.
2. Remove dirt, loose mortar, scale, efflorescence, or powder.
3. Previously painted masonry: SSPC-SP1; remove chalk and loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
L. Cement Plaster (Stucco):
1. Allow surfaces to cure for 30 to 60 days prior to coating.
2. Fill minor isolated hairline cracks with patching plaster and smooth off to match texture of adjacent surfaces.
3. Remove dirt, loose material, scale, efflorescence, powder, and other foreign matter. Remove oil and grease by washing with a tri-sodium phosphate solution, rinse with clean, clear water and let thoroughly dry.
M. Gypsum Wallboard Surfaces:
1. Fill narrow, shallow cracks and small holes with spackling compound.
2. Rake deep, wide cracks and deep holes; dampen with clean, clear water and fill with thin layers of joint cement.
N. Wood Surfaces:
1. Sand wood surfaces and edges smooth and even before finishing and between coats. Remove dust after each sanding.
2. Remove residue from knots, pitch streaks, cracks, open joints and sappy spots. Coat knots with a pigmented stain sealer prior to coating.
3. Countersink nails and fill nail holes, cracks, open joints and other defects with tinted putty or wood filler after priming is dry and before the second coat.
O. Brick or Concrete Surfaces to Receive Penetrating Water Repellent:
1. Surfaces shall be sound, dry and free of cracks, dirt, oils, paint or other contaminants which may affect the penetration of the clear penetrating water repellent.
2. Fill all cracks and voids, and tuck-point mortar joints if necessary. New mortar must cure a minimum of twenty-one (21) days before treatment.
3. Surface and air temperature must be above 40 degrees F.
P. Insulated Pipe Coverings, Canvas or PVC Jacket:
1. Clean using high-pressure air and solvent of the type recommended by the coating manufacturer.
Q. Polyvinyl Chloride (PVC) Pipe:
1. Remove ink markings by wiping down with clean, lint-free cloths saturated with denatured alcohol. Uniformly sand the surface with 150-200 grit sandpaper and wipe off dust residue.
R. Moisture Emission Test for Concrete and Masonry:
1. Test substrates for moisture prior to application of coating systems by the plastic sheet method in compliance with ASTM D4263.
S. Materials Preparation: Carefully mix and prepare coating materials according to the manufacturer's directions.
1. Maintain containers used in mixing and applying coatings in a clean condition, free of foreign materials and residue.
2. Stir material before application to produce a mixture of uniform density; stir as required during application. Do not stir surface film into material. Remove film and, if necessary, strain material before using.
3. Use only thinners approved by the coating manufacturer and only within recommended limits.
T. Tinting: Tint each undercoat a lighter shade to facilitate identification of each coat where multiple coats of the same material are applied. Tint undercoats to match the color of the finish coat but provide sufficient differences in shade of undercoats to distinguish each separate coat.
U. SSPC/NACE Surface Preparation Standards — Reference Descriptions:
1. SSPC-SP1 — Solvent Cleaning: Removes all visible oil, grease, soil, drawing/cutting compounds, and other soluble contaminants by wiping, spraying, immersion, vapor degreasing, alkaline cleaning, or steam cleaning. Does not remove rust, mill scale, or old coating.
2. SSPC-SP2 — Hand Tool Cleaning: Removes loose mill scale, loose rust, and loose paint using non-powered hand tools. Tightly adherent material that passes the dull-putty-knife test may remain.
3. SSPC-SP3 — Power Tool Cleaning: Same intent as SP2 but performed with powered tools. Must not leave burrs, sharp ridges, or gouges in the substrate.
4. SSPC-SP5 / NACE No. 1 — White Metal Blast Cleaning: Abrasive blast to bare metal removing all mill scale, rust, coating, and foreign matter; no staining or residue permitted.
5. SSPC-SP6 / NACE No. 3 — Commercial Blast Cleaning: Abrasive blast to bare metal on at least 66-2/3 percent of each 3 in. x 3 in. area; remaining area may show only light shadows, streaks, or slight discoloration.
6. SSPC-SP7 / NACE No. 4 — Brush-Off Blast Cleaning: Abrasive blast removing loose mill scale, loose rust, and loose coating; tightly adherent material may remain.
7. SSPC-SP10 / NACE No. 2 — Near-White Metal Blast Cleaning: Abrasive blast to bare metal on at least 95 percent of each unit area; remaining 5 percent limited to light shadows, streaks, or discoloration.
8. SSPC-SP11 — Power Tool Cleaning to Bare Metal: Power tool cleaning to bare metal with a minimum 1-mil surface profile; minor rust or staining may remain in pits.
9. SSPC-SP WJ-1 to WJ-4/NACE WJ-1 to WJ-4 — High- and Ultra-High-Pressure Water Jetting: Water jetting to one of four cleanliness grades, WJ-1 through WJ-4. Water jetting alone does not profile the substrate.
10. SSPC-SP13 / NACE No. 6 — Surface Preparation of Concrete: Prepares concrete by mechanical, chemical, or thermal means to remove laitance, curing compound, and contaminants and to achieve a sound, uniform profile; profile depth described using ICRI Concrete Surface Profile (CSP) chips 1-10 per ICRI Guideline 310.2R.
11. SSPC-SP14 / NACE No. 8 — Industrial Blast Cleaning: Abrasive blast to bare metal on at least 90 percent of each unit area.
12. SSPC-SP15 — Commercial Grade Power Tool Cleaning: Power tool cleaning to bare metal with a defined profile; random staining may remain on no more than 33 percent of each unit area.
13. SSPC-SP16 — Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steel, and Non-Ferrous Metals: Light abrasive blast that removes loose contaminants and lightly profiles the surface without removing all galvanizing or base metal.
14. SSPC-SP17 — Thorough Abrasive Blast Cleaning of Non-Ferrous Metals: More thorough than SP16; removes all loose material while limiting profile depth and base-metal removal.
15. SSPC-SP18 — Thorough Spot and Sweep Blast Cleaning for Industrial Coating Maintenance: Blast cleaning for maintenance recoat work that removes loose material and feathers edges around sound, tightly adherent existing coating.
3.3 APPLICATION
A. General: Apply coatings according to the manufacturer's directions. Use applicators and techniques best suited for the substrate and type of material being applied.
B. Do not coat over dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions detrimental to formation of a durable coating film.
C. Coating colors, surface treatments, and finishes are indicated in the schedules. Provide finish coats that are compatible with primers used.
D. The number of coats and the film thickness required are the same regardless of the application method. Do not apply succeeding coats until the previous coat has cured as recommended by the manufacturer. Sand between applications where sanding is required to produce a smooth even surface according to the manufacturer's directions.
E. Apply additional coats if undercoats, stains, or other conditions show through the final coat until the coating film is of uniform finish, color, and appearance. Give special attention to ensure that surfaces, including edges, corners, crevices, welds, and exposed fasteners, receive a dry film thickness equivalent to that of flat surfaces.
F. Stripe Coats: Apply stripe coats by brush to all welds, edges, corners, bolts, rivets, crevices and irregular surfaces where scheduled, prior to the full intermediate coat.
G. The term "exposed surfaces" includes areas visible when permanent or built-in fixtures, grilles, and similar components are in place. Extend coatings in these areas as required to maintain the system integrity and provide the desired protection.
H. Coat surfaces behind movable equipment the same as similar exposed surfaces. Before final installation of equipment, coat surfaces behind permanently fixed equipment with prime coat only.
I. Omit primer on metal surfaces that have been shop-primed and touch-up coated.
J. Scheduling: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for coating as soon as practicable after preparation and before subsequent surface deterioration; coat abrasive-blasted steel before visible rust forms and within 8 hours of blasting.
K. Allow sufficient time between successive coats to permit proper drying. Do not recoat until the coating has dried to where it feels firm, does not deform or feel sticky under moderate thumb pressure, and where application of another coat does not cause the undercoat to lift or lose adhesion. Observe maximum recoat windows on the product data sheet; where exceeded, prepare the surface as recommended by the manufacturer.
L. Potable Water Service: Cure linings in contact with potable water for the time and at the conditions required by the manufacturer's product data sheet and the NSF listing before placing in service; force-cure with heated, dehumidified air where required to meet the schedule. After cure, disinfect storage tanks in accordance with ANSI/AWWA C652 and pipe in accordance with ANSI/AWWA C651 before filling.
M. Application Procedures: Apply coatings by brush, roller, spray, or other applicators according to the manufacturer's directions.
1. Brushes: Use brushes best suited for the material applied.
2. Rollers: Use rollers of carpet, velvet back, or high-pile sheep's wool as recommended by the manufacturer for the material and texture required.
3. Spray Equipment: Use airless or plural-component spray equipment with orifice size as recommended by the manufacturer for the material and texture required.
N. Minimum Coating Thickness: Apply materials no thinner than the manufacturer's recommended spreading rate. Provide the total dry film thickness of the entire system as scheduled.
O. Mechanical items to be coated include, but are not limited to, the following:
1. Piping, pipe hangers, and supports.
2. Insulation.
3. Motors and mechanical equipment.
4. Accessory items.
P. Electrical items to be coated include, but are not limited to, the following:
1. Conduit and fittings.
Q. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled.
R. Prime Coats: Before applying finish coats, apply a prime coat of material, as recommended by the manufacturer, to material that is required to be coated and that has not been prime-coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas appears, to ensure a finish coat with no burn-through or other defects due to insufficient sealing.
S. Pigmented (Opaque) Finishes: Completely cover to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable.
T. Completed Work: Match approved samples for color, texture, and coverage. Remove, refinish, or recoat work not complying with specified requirements.
3.4 FIELD QUALITY CONTROL
A. Verify DFT of each coat and total DFT of each system using wet film and dry film gauges in accordance with SSPC-PA 2.
B. Immersion Linings: Perform holiday (discontinuity) testing of all immersion linings on steel, ductile iron and concrete in accordance with AMPP SP0188 (low-voltage sponge for linings less than 20 mils; high-voltage per NACE SP0274 for thicker linings) after final cure and before placing in service; mark and repair all holidays and retest.
C. Adhesion: Where directed by the Engineer, perform pull-off adhesion testing in accordance with ASTM D4541 on the mock-up or test area; repair test locations.
D. The Owner reserves the right to invoke the following test procedure at any time and as often as the Owner deems necessary during the period when coatings are being applied:
1. The Owner will engage the services of an independent testing agency to sample the coating material being used. Samples of material delivered to the Project will be taken, identified, sealed, and certified in the presence of the Contractor.
2. The testing agency will perform appropriate tests for the following characteristics as required by the Owner:
a. Quantitative materials analysis.
b. Abrasion resistance.
c. Apparent reflectivity.
d. Flexibility.
e. Washability.
f. Absorption.
g. Accelerated weathering.
h. Dry opacity.
i. Accelerated yellowness.
j. Recoating.
k. Skinning.
l. Color retention.
m. Alkali and mildew resistance.
3. If test results show material being used does not comply with specified requirements, the Contractor may be directed to stop coating, remove noncomplying coating, pay for testing, recoat surfaces coated with rejected material, and remove rejected material from previously coated surfaces if, upon recoating with the specified coating, the two coatings are incompatible.
3.5 CLEANING
A. At the end of each work day, remove empty cans, rags, rubbish, and other discarded coating materials from the site.
B. After completing coating work, clean glass and coating-spattered surfaces. Remove spattered coating by washing and scraping. Be careful not to scratch or damage adjacent finished surfaces.
3.6 PROTECTION
A. Protect work of other trades, whether being coated or not, against damage by coating work. Correct damage by cleaning, repairing or replacing, and recoating, as acceptable to the Engineer.
B. Provide "Wet Paint" signs to protect newly coated finishes. Remove temporary protective wrappings provided by others to protect their work after completing coating operations.
C. At completion of construction activities of other trades, touch up and restore damaged or defaced coated surfaces.
3.7 COATING SYSTEM SCHEDULE
Specifier Note: Systems below are identified by ACC's standard system codes. The potable-water immersion and tank-exterior systems are listed first; the shared interior, exterior and flooring systems that follow are the same definitions used in Sections 09 96 00 and 09 67 23 and are repeated here so this Section can stand alone for a plant project. Retain only the systems required and delete the remainder; add a bracketed list of typical locations (e.g., "[clearwell walls and floor, filter gallery piping]" or "[elevated tank exterior, ground storage tank interior]") after each system heading. Total DFT excludes stripe, touch-up and spot-prime coats and coats applied at coverage rate, as noted.
WATER-SPECIFIC SYSTEMS — POTABLE WATER IMMERSION (NSF/ANSI/CAN 61 AND 600) AND TANK EXTERIORS
A. Steel and Ductile Iron — Potable Water Systems (PW-S1)
Note: NSF/ANSI/CAN 61 certified products are required for surfaces in contact with potable water. Exterior and non-immersion systems (PW-S1.3, PW-S1.6, PW-S1.7) do not require NSF/ANSI/CAN 61 certification.
1. Tanks, Structural Steel and Equipment — Immersion, 100% Solids Epoxy (Best) (System PW-S1.1)
a. Surface Preparation: SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning.
b. Primer: Series 93-H2O Hydro-Zinc, DFT 2.5 - 3.5 mils.
c. Stripe Coat: Series 21 Epoxoline, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 22 / FC22 Epoxoline, DFT 20.0 - 30.0 mils.
e. Total DFT: 22.5 - 33.5 (excludes stripe coats).
Note: NSF/ANSI/CAN 61 certification of Series 22 applies only to colors 22-WH11, 22-1218 and 22-1255.
2. Tanks, Structural Steel and Equipment — Immersion, High Solids Epoxy (Good) (System PW-S1.2)
a. Surface Preparation: SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning.
b. Primer: Series 93-H2O Hydro-Zinc, DFT 2.5 - 3.5 mils.
c. Stripe Coat: Series 21 Epoxoline, DFT 3.0 - 5.0 mils.
d. Finish Coat: Series 21 Epoxoline, DFT 12.0 - 14.0 mils.
e. Total DFT: 14.5 - 17.5 (excludes stripe coats).
3. Tanks, Structural Steel and Equipment — Exterior, Non-Immersion (System PW-S1.3)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Primer: Series 93-H2O Hydro-Zinc, DFT 2.5 - 3.5 mils.
c. Stripe Coat: Series 21 Epoxoline, DFT 4.0 - 6.0 mils.
d. Intermediate Coat: Series 21 Epoxoline, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 1095 Endura-Shield, DFT 2.0 - 3.0 mils.
f. Total DFT: 8.5 - 12.5 (excludes stripe coats).
4. Steel Pipe — Immersion (System PW-S1.4)
a. Surface Preparation: SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning.
b. Primer: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
c. Intermediate: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
d. Finish Coat: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
e. Total DFT: 12.0 - 15.0 mils.
Note: NSF/ANSI/CAN 61 listings carry minimum pipe diameter and tank size limits; confirm the current Series 21 listing at www.nsf.org for the project.
5. Ductile Iron Pipe, Valves and Fittings — Immersion (System PW-S1.5)
a. Surface Preparation: Reference NAPF 500-03-04.
b. Primer: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
c. Intermediate: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
d. Finish Coat: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
e. Total DFT: 12.0 - 15.0 mils.
6. Steel Pipe — Exterior, Non-Immersion (System PW-S1.6)
a. Surface Preparation: SSPC-SP6/NACE No. 3 (shop); lightly scarify shop coat, clean and dry (field).
b. Primer: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
c. Intermediate: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
d. Finish Coat: Series 1095 Endura-Shield, DFT 2.0 - 3.0 mils.
e. Total DFT: 10.0 - 13.0 mils.
7. Ductile Iron Pipe, Valves and Fittings — Exterior, Non-Immersion (System PW-S1.7)
a. Surface Preparation: Reference NAPF 500-03-04.
b. Primer: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
c. Intermediate: Series 21 Epoxoline, DFT 4.0 - 5.0 mils.
d. Finish Coat: Series 1095 Endura-Shield, DFT 2.0 - 3.0 mils.
e. Total DFT: 10.0 - 13.0 mils.
B. Concrete — Potable Water Immersion (NSF/ANSI/CAN 61 & 600) (PW-C1)
1. Cast-in-Place Concrete — 100% Solids Epoxy (Best) (System PW-C1.1)
a. Surface Preparation: SSPC-SP13/NACE No. 6, ICRI-CSP 5 or greater.
b. Surfacer / Filler (1/4"–4"): Series 217 MortarCrete, Applied at coverage rate.
c. Surfacer / Filler (1/8"–1"): Series N218 MortarClad, Applied at coverage rate.
d. Primer: Series 21 Epoxoline, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 22 / FC22 Epoxoline, DFT 20.0 - 30.0 mils.
f. Total DFT: 24.0 - 36.0 (over surfacer/filler applied as needed — not a rated coat).
Note: NSF/ANSI/CAN 61 certification of Series 22 applies only to colors 22-WH11, 22-1218 and 22-1255.
2. Cast-in-Place Concrete — High Solids Epoxy (Good) (System PW-C1.2)
a. Surface Preparation: SSPC-SP13/NACE No. 6, ICRI-CSP 3 or greater.
b. Surfacer / Filler (1/4"–4"): Series 217 MortarCrete, Applied at coverage rate.
c. Surfacer / Filler (1/8"–1"): Series N218 MortarClad, Applied at coverage rate.
d. Primer: Series 21 Epoxoline, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 21 Epoxoline, DFT 12.0 - 14.0 mils.
f. Total DFT: 16.0 - 20.0 (over surfacer/filler applied as needed — not a rated coat).
C. Secondary Containment (Chemical-Specific) (WW-C2)
1. Reinforced Novolac / Vinyl Ester Lining — Acid, Caustic, Oxidizer, Coagulant, Dechlorination, Organic (System WW-C2.1)
a. Surface Preparation: SSPC-SP13/NACE No. 6, ICRI-CSP 3-5; clean and dry.
b. Block Filler (CMU only): Series 130 Envirofill, 60-80 SF/Gal.
c. Cant Cove: Trowelable lining at floor-to-wall transitions, Embedded wet (not rated).
d. Primer: Series 201 Epoxoprime, DFT 6.0 - 8.0 mils.
e. Base Coat: Series 239SC ChemBloc, DFT 8.0 - 12.0 mils.
f. Reinforcement: 3/4-oz fiberglass mat, Embedded wet (not rated).
g. Saturant: Series 239SC ChemBloc, DFT 16.0 - 18.0 mils.
h. Finish Coat: Series 282 Tneme-Glaze, DFT 6.0 - 8.0 mils.
i. Total DFT: 36.0 - 46.0 (over block filler applied at coverage rate).
D. Condensation Mitigation / Thermal Insulating Coating (WW-S3)
1. Aerogel Insulative Coating on Steel Pipe, Tanks and Structure (System WW-S3.1)
a. Surface Preparation: SSPC-SP15 minimum (SSPC-SP6 preferred).
b. Primer: Series 394 PerimePrime, DFT 2.5 - 3.5 mils.
c. First Coat: Series 971 Aerolon, DFT 40.0 - 50.0 mils.
d. Intermediate: Series 971 Aerolon, DFT 40.0 - 50.0 mils.
e. Finish Coat: Series 971 Aerolon, DFT 40.0 - 50.0 mils.
f. Topcoat (exposed to view): Series 1028 Enduratone, DFT 2.0 - 3.0 mils.
g. Total DFT: 124.5 - 156.5 mils.
Shared Interior Systems — Process and Support Buildings
E. New or Previously Uncoated CMU (C1)
1. Moderate Duty, Water Based (System C1.2)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Block Filler: Series 130 Envirofill, 60-80 SF/Gal.
c. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0 (over block filler applied at coverage rate).
2. Moderate Duty, Solvent Based (System C1.3)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Block Filler: Series 130 Envirofill, 60-80 SF/Gal.
c. First Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0 (over block filler applied at coverage rate).
3. Moderate/Heavy Duty, Water Based w/ Urethane Finish (System C1.4)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Block Filler: Series 130 Envirofill, 60-80 SF/Gal.
c. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
e. Total DFT: 6.0 - 9.0 (over block filler applied at coverage rate).
4. Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish (System C1.5)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Block Filler: Series 1254 Epoxoblock WB, ~100 SF/Gal (CMU).
c. First Coat: Series 280 Tneme-Glaze, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
e. Total DFT: 6.0 - 9.0 (over block filler applied at coverage rate).
5. Moderate/Heavy Duty, Chemical Resistant (System C1.6)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Block Filler: Series 130 Envirofill, 60-80 SF/Gal.
c. First Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0 (over block filler applied at coverage rate).
6. Heavy Duty / Washdown, 100% Solids Reinforced (System C1.7)
a. Surface Preparation: Clean and dry; allow new CMU and mortar to cure a minimum of 28 days; remove efflorescence, loose mortar and dust.
b. Filler: Series 215 Surfacing Epoxy, 25-40 SF/Gal.
c. Glass Mat: Series 273 ML Stranlok, embedded into wet Series 215, Embedded wet.
d. Saturant: Series 280 Tneme-Glaze, DFT 8.0 - 10.0 mils.
e. Intermediate: Series 280 Tneme-Glaze, DFT 6.0 - 8.0 mils.
f. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
g. Total DFT: 16.0 - 21.0 (over surfacer/filler applied as needed — not a rated coat).
F. New or Previously Uncoated Concrete (C2)
1. Moderate Duty, Water Based (System C2.2)
a. Surface Preparation: SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
2. Moderate Duty, Solvent Based (System C2.3)
a. Surface Preparation: SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
3. Moderate/Heavy Duty, Water Based w/ Urethane Finish (System C2.4)
a. Surface Preparation: SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
f. Total DFT: 6.7 - 10.5 (over surfacer/filler applied as needed — not a rated coat).
4. Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish (System C2.5)
a. Surface Preparation: SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 280 Tneme-Glaze, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
f. Total DFT: 6.7 - 10.5 (over surfacer/filler applied as needed — not a rated coat).
5. Moderate/Heavy Duty, Chemical Resistant (System C2.6)
a. Surface Preparation: SSPC-SP13/NACE No. 6 Surface Preparation of Concrete; ICRI-CSP 2-3; clean, dry, cured a minimum of 28 days.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
G. Existing / Previously Painted CMU and Concrete (C3)
1. Moderate Duty, Water Based (System C3.2)
a. Surface Preparation: SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
2. Moderate Duty, Solvent Based (System C3.3)
a. Surface Preparation: SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
3. Moderate/Heavy Duty, Water Based w/ Urethane Finish (System C3.4)
a. Surface Preparation: SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 288/289 Enviro-Pox, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
f. Total DFT: 6.7 - 10.5 (over surfacer/filler applied as needed — not a rated coat).
4. Moderate/Heavy Duty, 100% Solids Epoxy w/ Urethane Finish (System C3.5)
a. Surface Preparation: SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 280 Tneme-Glaze, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 297 Enviro-Glaze, DFT 2.0 - 3.0 mils.
f. Total DFT: 6.7 - 10.5 (over surfacer/filler applied as needed — not a rated coat).
5. Moderate/Heavy Duty, Chemical Resistant (System C3.6)
a. Surface Preparation: SSPC-SP1; remove chalk/loose paint, patch cracks, spot prime bare areas, dull glossy surfaces.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. Filler (as needed): Series 215 Surfacing Epoxy, Applied at coverage rate.
d. First Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
f. Total DFT: 8.7 - 13.5 (over surfacer/filler applied as needed — not a rated coat).
H. Concrete Ceilings – New, Existing Painted or Structural, Plank and Deck (C4)
1. Dry-Fall, High-Moisture / Natatorium Ceilings (System C4.1)
a. Surface Preparation: SSPC-SP13/NACE No. 6; clean and dry; remove loose/peeling coating on previously painted ceilings.
b. Primer: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
c. Intermediate: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
d. Finish Coat: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
e. Total DFT: 6.0 - 12.0 mils.
2. Flexible / Mildew-Resistant Ceilings (Locker Rooms) (System C4.2)
a. Surface Preparation: SSPC-SP13/NACE No. 6; clean and dry; remove loose/peeling coating on previously painted ceilings.
b. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. First Coat: Series 158 Bio-Lastic, DFT 6.0 - 7.0 mils.
d. Finish Coat: Series 158 Bio-Lastic, DFT 6.0 - 7.0 mils.
e. Total DFT: 12.7 - 15.5 mils.
I. New or Previously Uncoated Steel (S1)
1. Moderate Duty, Solvent Based Epoxy (System S1.2)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
c. Touch-Up Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
d. First Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
f. Total DFT: 10.5 - 15.5 (excludes touch-up coats).
Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments.
2. Moderate Duty, Solvent Based Epoxy w/ Urethane Finish (System S1.3)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
c. Touch-Up Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
d. First Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
f. Total DFT: 9.5 - 13.5 (excludes touch-up coats).
Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments.
Note: Use Series 1090 as the finish coat for high traffic areas
3. Heavy Duty, Chemical Resistant Epoxy (System S1.4)
a. Surface Preparation: SSPC-SP10/NACE No. 2 Near-White Metal Blast Cleaning.
b. Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
c. Touch-Up Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
d. First Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
e. Stripe Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
f. Finish Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
g. Total DFT: 10.5 - 15.5 (excludes stripe/touch-up coats).
4. Overhead Structural Steel / Joists / Deck, Dry-Fall (System S1.5)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
c. Touch-Up Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
d. First Coat: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
e. Finish Coat: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
f. Total DFT: 6.5 - 11.5 (excludes touch-up coats).
Note: Specify Series 90-97 Tneme-Zinc for natatorium and/or wet environments.
5. Galvanized Steel, Epoxy Finish (System S1.6)
a. Surface Preparation: SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile.
b. First Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
6. Galvanized Steel, Urethane Finish (System S1.7)
a. Surface Preparation: SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile.
b. First Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
7. Galvanized Steel, Light Architectural Duty (System S1.8)
a. Surface Preparation: SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile.
b. Primer: Series 116 Uni-Bond, DFT 2.0 - 4.0 mils.
c. Finish Coat: Series 1028 Enduratone, DFT 2.0 - 3.0 mils.
d. Total DFT: 4.0 - 7.0 mils.
J. Existing / Previously Painted Steel (S2)
1. Moderate Duty, Solvent Based Epoxy Finish (System S2.2)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges.
b. Spot Prime: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
c. First Coat: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0 (excludes spot-prime coats).
2. Moderate Duty, Solvent Based Epoxy w/ Urethane Finish (System S2.3)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges.
b. Spot Prime: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
c. First Coat: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
e. Total DFT: 7.0 - 10.0 (excludes spot-prime coats).
Note: Use Series 1090 as the finish coat for high traffic areas
3. Heavy Duty, Chemical Resistant Epoxy (System S2.4)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning; SSPC-SP11 to bare metal at corroded areas; feather transition edges.
b. Touch-Up Primer: Series 1 Omnithane, DFT 2.5 - 3.5 mils.
c. First Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 104 H.S. Epoxy, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0 (excludes touch-up coats).
4. Overhead Structural Steel / Joists / Deck, Dry-Fall (System S2.5)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges.
b. Spot Prime: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
c. First Coat: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
d. Finish Coat: Series 115 Uni-Bond DF, DFT 2.0 - 4.0 mils.
e. Total DFT: 8.0 - 14.0 mils.
5. Galvanized Steel, Epoxy Finish (System S2.6)
a. Surface Preparation: SSPC-SP1; SSPC-SP2/SP3 to degloss and remove loose coating; SSPC-SP16 at exposed galvanizing.
b. First Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
6. Galvanized Steel, Urethane Finish (System S2.7)
a. Surface Preparation: SSPC-SP1; SSPC-SP2/SP3 to degloss and remove loose coating; SSPC-SP16 at exposed galvanizing.
b. First Coat: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
7. Hollow Metal Doors, Frames, Railings — Moderate/Heavy Duty (System S2.9)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges.
b. Primer: Series 27 Typoxy, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1090 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
K. Miscellaneous Interior Substrates (M1)
1. PVC Pipe, Trim and Plastic Components (System M1.2)
a. Surface Preparation: Solvent clean and dry; lightly sand with #150-200 sandpaper.
b. First Coat: Series 1028/1029 Enduratone, DFT 2.0 - 3.0 mils.
c. Finish Coat: Series 1028/1029 Enduratone, DFT 2.0 - 3.0 mils.
d. Total DFT: 4.0 - 6.0 mils.
2. Insulated Pipe Jacketing (Canvas / PVC Jacket) (System M1.3)
a. Surface Preparation: Clean and dry.
b. First Coat: Series 1026 Enduratone, DFT 2.0 - 3.0 mils.
c. Finish Coat: Series 1026 Enduratone, DFT 2.0 - 3.0 mils.
d. Total DFT: 4.0 - 6.0 mils.
3. Interior Aluminum and Non-Ferrous Metal (System M1.4)
a. Surface Preparation: SSPC-SP1; light abrasive sweep blast or uniformly sand to profile; avoid damaging/warping thin components.
b. Primer: Series 116 Uni-Bond, DFT 2.0 - 4.0 mils.
c. Finish Coat: Series 1028/1029 Enduratone, DFT 2.0 - 3.0 mils.
d. Total DFT: 4.0 - 7.0 mils.
Shared Exterior Systems
L. New or Previously Uncoated CMU and Concrete (EC1)
1. Elastomeric / Crack-Bridging, Smooth Finish (System EC1.1)
a. Surface Preparation: SSPC-SP13/NACE No. 6; clean, dry, free of oil/grease/form-release agents; allow new concrete/CMU to cure min. 14 days; repair cracks per mfr procedure.
b. Block Filler (CMU, as needed): Series 130 Envirofill, 60-80 SF/Gal.
c. Primer: Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
d. First Coat: Series 156 Enviro-Crete, DFT 6.0 - 8.0 mils.
e. Finish Coat: Series 156 Enviro-Crete, DFT 6.0 - 8.0 mils.
f. Total DFT: 12.7 - 17.5 (over block filler applied at coverage rate).
M. Existing / Previously Painted CMU, Brick and Concrete (EC2)
1. Elastomeric / Crack-Bridging Recoat (System EC2.1)
a. Surface Preparation: Power wash; remove loose/peeling coating and chalk; clean and dry.
b. Primer (as needed): Series 151-1051 Elasto-Grip FC, DFT 0.7 - 1.5 mils.
c. First Coat: Series 156 Enviro-Crete, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 156 Enviro-Crete, DFT 4.0 - 6.0 mils.
e. Total DFT: 8.0 - 12.0; optional Primer (as needed) 0.7 - 1.5 mils.
N. New or Full-Coating-Removal Steel (ES1)
1. Zinc / Epoxy / Urethane (Good) (System ES1.1)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Shop or Field Primer: Series 90-97 Tneme-Zinc, DFT 2.5 - 3.5 mils.
c. Touch-Up Primer: Series 90G-1K97 Tneme-Zinc, DFT 2.5 - 3.5 mils.
d. Intermediate: Series V69 Hi-Build Epoxoline II, DFT 4.0 - 6.0 mils.
e. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
f. Total DFT: 9.5 - 13.5 (excludes touch-up coats).
Note: Use Series 1090 as the finish coat for high traffic areas
O. Existing / Previously Painted Steel (Overcoat) (ES2)
1. Epoxy Mastic / Urethane (Good) (System ES2.1)
a. Surface Preparation: SSPC-SP2/SP3 Hand/Power Tool Cleaning; remove loose coating; feather transition edges.
b. Spot Prime: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
c. Full Prime Coat: Series 135 Chembuild, DFT 4.0 - 6.0 mils.
d. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
e. Total DFT: 7.0 - 10.0 (excludes spot-prime coats).
Note: Use Series 1090 as the finish coat for high traffic areas
P. Galvanized Steel (ES3)
1. New or Full Coating Removal, Urethane Finish (Good) (System ES3.1)
a. Surface Preparation: SSPC-SP1 to remove oil/grease/contaminants; SSPC-SP16 to remove storage stains and uniformly profile.
b. Primer: Series V69 Hi-Build Epoxoline II, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
2. Previously Coated Galvanized, Overcoat (System ES3.3)
a. Surface Preparation: Wash clean; SSPC-SP2/SP3 Hand/Power Tool Cleaning to degloss; remove loose coatings; feather transition edges.
b. Spot / Prime Coat: Series 27 Typoxy, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Optional Finish: Series 1070V Fluoronar, DFT 2.0 - 3.0 mils.
e. Total DFT: 6.0 - 8.0; Optional Finish 2.0 - 3.0 mils.
Q. Aluminum and Non-Ferrous Metal (ES4)
1. General (System ES4.1)
a. Surface Preparation: Light abrasive sweep blast (SSPC-SP16), uniform angular profile 1.0-2.0 mils; avoid damaging/warping thin components.
b. Primer: Series V69 Hi-Build Epoxoline II, DFT 2.0 - 3.0 mils.
c. Intermediate: Series 1095 Endura-Shield, DFT 2.0 - 3.0 mils.
d. Finish Coat: Series 1071 Fluoronar, DFT 2.0 - 3.0 mils.
e. Total DFT: 6.0 - 9.0 mils.
R. Hollow Metal Doors and Frames (ES5)
1. Hollow Metal Doors, Frames, Railings — Moderate/Heavy Duty (System ES5.2)
a. Surface Preparation: Uniformly scarify to remove glaze/sheen (test patch required).
b. Primer: Series 27 Typoxy, DFT 3.0 - 4.0 mils.
c. Finish Coat: Series 1095 Endura-Shield, DFT 3.0 - 4.0 mils.
d. Total DFT: 6.0 - 8.0 mils.
Note: Use Series 1090 as the finish coat for high traffic areas
S. Wood (EW1)
1. Bare or Previously Painted (System EW1.1)
a. Surface Preparation: Clean and dry; sand smooth.
b. Primer: Series V10 Tnemec Primer, DFT 2.0 - 3.5 mils.
c. First Coat: Series 1028 Enduratone, DFT 2.0 - 3.0 mils.
d. Finish Coat: Series 1028 Enduratone, DFT 2.0 - 3.0 mils.
e. Total DFT: 6.0 - 9.5 mils.
T. Water Repellents, Sealers and Anti-Graffiti (ESL1)
1. Penetrating Silane/Siloxane Water Repellent (System ESL1.1)
a. Surface Preparation: Per product surface-absorption test; clean, dry, free of efflorescence.
b. Sealer: Series 633 Prime-A-Pell H2O (Tnemec) — or Tex-Cote Rainstopper 120/140, N/A (penetrating sealer).
c. Total DFT: Not applicable — penetrating sealer, no measurable dry film thickness.
Shared Resinous Flooring Systems (See Section 09 67 23 for Full Flooring Requirements)
U. 100% Solids Epoxy Systems (E1)
1. 1/16" Solid Color Epoxy Broadcast — Light Duty (System E1.3)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 3 minimum.
b. Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
c. Primer: Series N222 Deco-Tread, 250-320 SF/gal.
d. Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand, 80-100 SF/gal.
e. Grout Coat: Series N222 Deco-Tread (pigmented), 160-200 SF/gal.
f. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
g. Total DFT: Nominal 1/16" system.
2. 1/8" Solid Color Epoxy Broadcast — Moderate Duty (System E1.4)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 3 minimum.
b. Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
c. Primer: Series N222 Deco-Tread, 250-320 SF/gal.
d. First Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand, 80-100 SF/gal.
e. Second Broadcast Coat: Series N222 Deco-Tread with 30/50 silica sand, 80-100 SF/gal.
f. Grout Coat: Series N222 Deco-Tread (pigmented), 160-200 SF/gal.
g. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
h. Total DFT: Nominal 1/8" system.
V. Water-Based Epoxy (WB1)
1. 1/16" Solid Color Epoxy Broadcast — Light Duty (System WB1.3)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 2-3 minimum.
b. Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
c. Primer: Series 288/289 Enviro-Pox, 250-320 SF/gal.
d. Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand, 80-100 SF/gal.
e. Grout Coat: Series 288/289 Enviro-Pox (pigmented), 160-200 SF/gal.
f. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
g. Total DFT: Nominal 1/16" system.
2. 1/8" Solid Color Epoxy Broadcast — Moderate Duty (System WB1.4)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 2-3 minimum.
b. Cove Base (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
c. Primer: Series 288/289 Enviro-Pox, 250-320 SF/gal.
d. First Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand, 80-100 SF/gal.
e. Second Broadcast Coat: Series 288/289 Enviro-Pox with 30/50 silica sand, 80-100 SF/gal.
f. Grout Coat: Series 288/289 Enviro-Pox (pigmented), 160-200 SF/gal.
g. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
h. Total DFT: Nominal 1/8" system.
W. Urethane Cement Systems (UC1)
1. 1/4" Solid Color Urethane Cement — Heavy Duty (System UC1.1)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 5 minimum.
b. Base / Broadcast Coat: Series N242 Ultra-Tread S with 30/50 aggregate, 37 SF/kit.
c. Coving (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
d. Grout Coat: Series N222 Deco-Tread (pigmented), 160-200 SF/gal.
e. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
f. Total DFT: Nominal 1/4" system.
2. 1/8" Solid Color Urethane Cement — Moderate/Heavy Duty (System UC1.3)
a. Surface Preparation: NACE No. 6/SSPC-SP13, shot-blast or mechanically abrade to ICRI-CSP 5 minimum.
b. Coving (where required): Series N283, N222 or 288 epoxy with aggregate, Applied at coverage rate.
c. Base / Broadcast Coat: Series N241 Ultra-Tread MVT with aggregate, 90 SF/kit.
d. Grout Coat: Series N222 Deco-Tread (pigmented), 160-200 SF/gal.
e. Finish Coat: Series 248 Everthane with 821 Field Colorant, 500-600 SF/gal.
f. Total DFT: Nominal 1/8" system.
Specialty Systems
X. Specialty Systems (X1)
1. Aerogel Thermal-Break Coating at Steel Envelope Penetrations (System X1.1)
a. Surface Preparation: SSPC-SP6/NACE No. 3 Commercial Blast Cleaning.
b. Primer: Series 394 PerimePrime, DFT 2.5 - 3.5 mils.
c. Insulative Coating (2–3 coats by shape): Series 971 Aerolon, 40.0 - 50.0 per coat (2 coats W-shapes / 3 coats HSS & deck).
d. Finish (exposed to view): Series 1028 Enduratone, DFT 2.0 - 3.0 mils.
e. Total DFT: 82.5 - 153.5 mils (per shape; 2 coats W-shapes, 3 coats HSS/deck) plus 2.0 - 3.0 mils finish where exposed.
3.8 COLOR SYSTEM — MATERIAL IDENTIFICATION
Specifier Note: Pipe and equipment identification colors below follow the common water/wastewater convention (Ten States Standards / AWWA practice) with the matching Tnemec color. Edit to the Owner's standard or delete if identification is specified elsewhere.
A. Piping and equipment shall be color coded as follows unless otherwise indicated on the Drawings:
Service | Generic Color | Tnemec Color |
Raw Water | Olive green | 110GN Clover |
Settled or Clarified Water | Aqua | 10GN Aqua Sky |
Finished or Potable Water | Dark blue | 11SF Safety Blue |
Sewage Plant Effluent | Clay | 07RD Terra Cotta |
Backwash Waste | Light brown | 68BR Twine |
Reclaimed Water | Light purple | R0715 Light Purple |
Sludge | Dark brown | 84BR Weathered Bark |
Sewer (sanitary or other) | Dark gray | GR28 Fossil |
Alum or Primary Coagulant | Orange | 04SF Safety Orange |
Ammonia | White | 11WH White |
Carbon Slurry | Black | 35GR Black |
Caustic | Yellow with green band | 02SF Safety Yellow / 09SF Safety Green |
Chlorine (gas and solution) | Yellow | 02SF Safety Yellow |
Fluoride | Light blue with red band | 25BL Fountainbleu / 06SF Safety Red |
Lime Slurry | Light green | PA30 Daiquiri Ice |
Ozone | Yellow with orange band | 02SF / 04SF |
Phosphate Compounds | Light green with red band | PA30 Daiquiri Ice / 06SF |
Polymers or Coagulant Aids | Orange with green band | 04SF / 09SF |
Potassium Permanganate | Violet | 14SF Safety Purple |
Soda Ash | Light green with orange band | PA30 Daiquiri Ice / 04SF |
Sulfuric Acid | Yellow with red band | 02SF / 06SF |
Sulfur Dioxide | Light green with yellow band | PA30 Daiquiri Ice / 02SF |
Compressed Air | Dark green | 91GN Balsam |
Gas | Red | 28RD Monterrey Tile |
Other Lines | Light gray | 32GR Light Gray |
Hoists / Trolleys | Yellow | 02SF Safety Yellow |
Fire Protection | Red | 06SF Safety Red |